Woodington Solar Farm

Woodington Solar Farm is under construction in Test Valley with a recorded capacity of 46 MW.

46 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Woodington Solar Limited
Test Valley
Authority
England

Planning and build timeline

Application submitted2015-11-17
Permission granted2017-07-04
20 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Test Valley’s record on solar

Test Valley has decided 37 solar farms and approved 95%, taking a median of 5 months. See every solar farm decision in Test Valley

Other built sites within 15 km

SiteMWDistance
Woodington Solar Farm (Central)
Solar Photovoltaics · Under Construction
0 km
Squabb Wood
Landfill Gas · Operational
13.1 km
Highwood Lane
Solar Photovoltaics · Operational
54.3 km
Grove Solar Park (Phase 1)
Solar Photovoltaics · Operational
56.7 km
Grove Solar Park (Phase 2)
Solar Photovoltaics · Operational
116.7 km
Mill Lane, Nursling - Battery Storage Facility
Battery · Under Construction
207.4 km
Testwood Water Supply Works
Solar Photovoltaics · Operational
1.97.8 km
Whiteparish
Landfill Gas · Operational
1.19.6 km

How big is Woodington Solar Farm?

Woodington Solar Farm has a recorded installed capacity of 46 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Woodington Solar Farm?

REPD records the operator as Woodington Solar Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Woodington Solar Farm approved and built?

The application was submitted on 2015-11-17. Permission was granted on 2017-07-04, 20 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5883.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council