Novarly ParcelRenewable sites

Renewable sitesHighwood Lane

Highwood Lane

Highwood Lane is an operational 5 MW solar farm in Test Valley, generating since 31 August 2016. Planning permission was granted on 22 July 2015, 3 months after submission. Operator of record: Solstice Renewables.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 31 August 2016
Solar Photovoltaics
Technology
Solstice Renewables
Test Valley
Authority
England

Planning and build timeline

Application submitted5 May 2015
Permission granted22 July 2015
3 months after submission
Operational31 August 2016
13 months after consent

Screening a site of your own?

RedlineUK · £39

Test Valley approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Highwood Lane’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Test Valley’s record on solar

Test Valley has decided 37 solar farms and approved 95%, taking a median of 5 months. See every solar farm decision in Test Valley

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
11.3 km
Solar Photovoltaics · Operational
53.5 km
Solar Photovoltaics · Operational
113.5 km
Solar Photovoltaics · Under Construction
464.3 km
Solar Photovoltaics · Under Construction
4.3 km
Battery · Under Construction
205.5 km
Solar Photovoltaics · Operational
1.96.4 km
Solar Photovoltaics · Operational
6.48.3 km

How big is Highwood Lane?

Highwood Lane has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Highwood Lane?

REPD records the operator as Solstice Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Highwood Lane approved and built?

The application was submitted on 5 May 2015. Permission was granted on 22 July 2015, 3 months later. The site became operational on 31 August 2016, 13 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5242.

Novarly Parcel · official public data, read properly · parcel.novarly.com