Solar planning in Test Valley

Test Valley has decided 37 solar farms and approved 95% of them, taking a median of 5 months to decide. Consented capacity: 406 MW. 6 applications still awaiting a decision.

95%
Approved
35 granted · 2 refused
5 mo
Median decision
UK 2.3 mo
406 MW
Consented
5 MW refused
4
Appeals
3 allowed on appeal

How Test Valley compares

Against the 298 UK authorities with 5+ solar decisions, Test Valley sits in the 43rd percentile for approval rate (2 points above the England average) and the 7th percentile for speed.

Decisions by year

510Approved — 3 (2011)311Approved — 2 (2012)Refused — 1 (2012)312Approved — 2 (2013)213Approved — 8 (2015)815Approved — 1 (2017)117Approved — 1 (2020)120Approved — 1 (2021)121Approved — 9 (2022)922Approved — 4 (2023)423Approved — 1 (2024)124Approved — 3 (2025)Refused — 1 (2025)425
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (48)

SchemeMWStatusDecided
Thruxton Airport, Amesbury Road - Solar Photovoltaic Panels
Thruxton Circuit Limited · 26/00173/REJN
0.23Application Submitted2026-01-30
Ocado Distribution Centre, South Way - Solar Panels
Saber Renewable Energy Limited · 25/01657/REJN · 1.8 mo to decide
Application Refused2025-09-19
Cholderton Road, Quarley - Solar Farm
Innova Renewables · 24/01288/FULLN · 11.2 mo to decide
22.5Awaiting Construction2025-05-14
South Way, Walworth Business Park - Solar Photovoltaics
Saber Renewable Energy Limited · 25/00252/REJN
5.2Application Withdrawn2025-04-30
Andover Leisure Centre, West Street - Solar Panels
Places for People Leisure · 25/00166/REJN · 1.8 mo to decide
0.25Awaiting Construction2025-03-18
Winchester Road, Wherwell - Solar Farm
RE Projects Development / Solarig · 23/02225/FULLN · 16.8 mo to decide
45.9Awaiting Construction2025-02-05
Tesco Distribution, Canberra Road - Solar PV Array
ABRDN (Investments Trust/Standard Life) · 24/02395/REJS
2.14Application Withdrawn2024-10-31
Preformed Line Products, East Portway - Solar Panels
GHE Solar Limited · 24/00325/FULLN · 2.1 mo to decide
0.27Awaiting Construction2024-05-08
Farleigh School, Stockbridge Road - Solar Panels
Farleigh School · 23/03188/FULLN
0.3Application Withdrawn2024-04-10
Cholderton Road, Quarley - Solar Farm
Novus Renewable Services Limited · 21/03760/FULLN · 20.4 mo to decide
22.5Revised2023-09-22
R Twining And Company, South Way - Solar Panels
Twinings · 23/01723/REJN · 1.1 mo to decide
0.98Awaiting Construction2023-08-09
Mauretania Road, Nursling - Solar Panels
SLI UK Real Estate Fund · 23/01795/REJS
0.19Application Submitted2023-07-12
Gander Down Solar Farm, Stevens Drove - Solar Farm
PS Renewables Limited · 22/02325/FULLS · 8.8 mo to decide
6.2Awaiting Construction2023-06-01
Danebury Works, Andover Hill - Solar Panels
SB Joinery UK Limited · 23/00497/REJN · 1.8 mo to decide
0.19Awaiting Construction2023-04-17
Randall Parker Foods, Back Lane - Solar PV Panels
EDF Energy Renewables · 23/00556/REJN · 13.5 mo to decide
0.17Awaiting Construction2023-04-14
Perham Down - Meadow Solar Farm & Battery Storage
Low Carbon UK Solar Investment Co Limited · 21/01749/FULLN · 17.3 mo to decide
49.9Awaiting Construction2022-11-18
South Park Solar Farm
Renewable Connections Developments Limited · 21/02997/FULLN · 12.7 mo to decide
15Awaiting Construction2022-11-03
Preformed Line Products, East Portway - Solar Panels
GHE Solar Limited · 22/02476/FULLN
0.34Revised2022-09-23
Woodington Road, East Wellow - Solar Panels
CPV Limited · 22/01891/REJS · 1.7 mo to decide
0.5Awaiting Construction2022-09-13
Walworth Business Park - Solar Photovoltaics panel
Cactus Energy / Sealock Limited · 22/01467/REJN · 1.6 mo to decide
0.25Awaiting Construction2022-07-20
Units 1 And 2, Assent 40, Plot 12, Portway Business Park - Solar Panels
Hoaward Tenens Limited · 22/01084/REJN · 2 mo to decide
0.36Awaiting Construction2022-06-20
Howard Tenens, Assent 100, Stephenson Close, - Solar Panels
Hoaward Tenens Limited · 22/01054/REJN · 2.2 mo to decide
0.94Awaiting Construction2022-06-20
Howard Tenens Limited, Plot 4, Portway Business Park - Solar Panels
Howard Tenens Limited · 22/01090/REJN · 2 mo to decide
0.7Awaiting Construction2022-06-20
Howard Tenens, Plot 5, West Portway - Solar Panels
Howard Tenens Limited · 22/01092/REJN · 2 mo to decide
0.59Awaiting Construction2022-06-20
Howard Tenens, Plot 2, West Portway - Solar Panels
Howard Tenens Limited · 22/01091/REJN · 2 mo to decide
0.3Awaiting Construction2022-06-20
Woodington Solar Farm (Central)
Woodington Solar Limited · 20/00814/FULLS · 13.3 mo to decide
Under Construction2021-05-24
Hatherden Farm
Nextpower SPV 10 Limited · 19/03043/FULLN · 5.5 mo to decide
49.9Operational2020-06-05
Woodington Solar Farm
Woodington Solar Limited · 15/02591/FULLS · 19.5 mo to decide
46Under Construction2017-07-04
Cowdown Lane
Equitix · 14/00949/FULLN · 19.8 mo to decide
40Operational2015-12-24
Fullenton Solar Farm
Tealing Solar Parks · 15/01401/FULLN · 5.6 mo to decide
4.2Operational2015-12-11
Churchers Common Solar Park
British Solar Renewables · 15/01399/FULLS · 5.4 mo to decide
5Abandoned2015-12-01
Grove Solar Park (Phase 2)
Solar Century · 14/01826/FULLS · 13.1 mo to decide
11Operational2015-09-04
Grove Solar Park (Phase 1)
Solar Century · 14/01826/FULLS · 13.1 mo to decide
5Operational2015-09-04
Eveley Farm
PS Renewables · 15/00094/FULLS · 5.3 mo to decide
49Operational2015-07-27
Highwood Lane
Solstice Renewables · 15/01001/FULLS · 2.6 mo to decide
5Operational2015-07-22
Lains Farm
INRG · 14/03017/FULLN · 7.4 mo to decide
5Operational2015-07-17
Abbots Ann
British Solar Renewables · 14/02110/FULLN · 4.6 mo to decide
7Operational2015-01-23
Manor Farm (Thruxton)
Lightsource Renewable Energy · 14/01830/FULLN
12.5Application Withdrawn2014-10-06
Eveley Farm
Kronos Solar · 13/02735/FULLS · 8.1 mo to decide
49Revised2014-08-15
Saxley Farm
Solar Century/ Bluefield Solar · 13/02122/FULLN · 2.7 mo to decide
5Operational2013-12-18
Westover Farm
Private Developer · 12/02707/FULLN · 3 mo to decide
7Operational2013-03-13
Westover Farm
SPGL (Solar Power Generation Limited) · 12/02159/FULLN
7Revised2012-12-11
Somborne Park Road
Private Developer · 12/01573/FULLN · 3.7 mo to decide
5Application Refused2012-11-22
Parkhouse Corner (Orta Solar)
Orta Solar · 12/01725/FULLN · 3.2 mo to decide
6.6Operational2012-11-14
Owls Lodge Farm Extension
Anesco · 12/01186/FULLN · 1.9 mo to decide
5Operational2012-09-05
Owls Lodge Farm
Anesco (previously AEE Renewables) · 11/00430/FULLN · 7.5 mo to decide
5Operational2011-10-07
Andover Solar Farm
The Clark Trustees · 11/00529/FULLN · 7 mo to decide
5Operational2011-09-29
Shipton Bellinger - Park House Corner Solar Farm
Low Carbon Solar · 11/00554/FULLN · 2.4 mo to decide
5.4Operational2011-05-17

Does Test Valley approve solar farms?

Yes — of the 37 solar farms Test Valley has decided, 95% were approved (35 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Test Valley?

The median time from application to decision is 5 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Test Valley consented?

406 MW has been consented across 35 approved schemes, with 5 MW refused. A further 6 applications awaits a decision.

Other technologies in Test Valley

Battery storage in Test ValleyOnshore wind in Test Valley

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.