Testwood Water Supply Works

Testwood Water Supply Works is an operational 1.9 MW solar farm in New Forest, generating since 24 August 2017. Planning permission was granted on 12 December 2016, 5 months after submission. Operator of record: Southern Water Services.

1.9 MW
Capacity
as recorded in REPD
Operational
Status
since 24 August 2017
Solar Photovoltaics
Technology
Southern Water Services
New Forest
Authority
England

Planning and build timeline

Application submitted15 July 2016
Permission granted12 December 2016
5 months after submission
Operational24 August 2017
8 months after consent

Screening a site of your own?

RedlineUK · £39

New Forest approves 75% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Testwood Water Supply Works’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

New Forest’s record on solar

New Forest has decided 20 solar farms and approved 75%, taking a median of 2.2 months. See every solar farm decision in New Forest

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
201 km
Solar Photovoltaics · Operational
53.7 km
Solar Photovoltaics · Operational
113.7 km
EfW Incineration · Operational
164.9 km
Solar Photovoltaics · Operational
5.35.1 km
Solar Photovoltaics · Operational
56.4 km
Landfill Gas · Operational
16.9 km
Solar Photovoltaics · Under Construction
7.8 km

How big is Testwood Water Supply Works?

Testwood Water Supply Works has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Testwood Water Supply Works?

REPD records the operator as Southern Water Services. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Testwood Water Supply Works approved and built?

The application was submitted on 15 July 2016. Permission was granted on 12 December 2016, 5 months later. The site became operational on 24 August 2017, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6329.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode