Renewable sites › Testwood Water Supply Works
Testwood Water Supply Works
Testwood Water Supply Works is operational in New Forest with a recorded capacity of 1.9 MW, and has been generating since 2017-08-24.
Planning and build timeline
| Application submitted | 2016-07-15 |
| Permission granted | 2016-12-12 5 months after submission |
| Operational | 2017-08-24 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Nutrient-neutrality catchment — Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
New Forest’s record on solar
New Forest has decided 20 solar farms and approved 75%, taking a median of 2.2 months. See every solar farm decision in New Forest →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Mill Lane, Nursling - Battery Storage Facility Battery · Under Construction | 20 | 1 km |
Grove Solar Park (Phase 1) Solar Photovoltaics · Operational | 5 | 3.7 km |
Grove Solar Park (Phase 2) Solar Photovoltaics · Operational | 11 | 3.7 km |
Marchwood ERF EfW Incineration · Operational | 16 | 4.9 km |
Tavells Lane Solar Farm Solar Photovoltaics · Operational | 5.3 | 5.1 km |
Highwood Lane Solar Photovoltaics · Operational | 5 | 6.4 km |
Squabb Wood Landfill Gas · Operational | 1 | 6.9 km |
Woodington Solar Farm (Central) Solar Photovoltaics · Under Construction | — | 7.8 km |
How big is Testwood Water Supply Works?
Testwood Water Supply Works has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Testwood Water Supply Works?
REPD records the operator as Southern Water Services. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Testwood Water Supply Works approved and built?
The application was submitted on 2016-07-15. Permission was granted on 2016-12-12, 5 months later. The site became operational on 2017-08-24, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6329.
Novarly Parcel · official public data, read properly · parcel.novarly.com