Renewable sites › Squabb Wood
Squabb Wood
Squabb Wood is an operational 1 MW landfill gas site in Test Valley, generating since 1 January 2006. Planning permission was granted on 14 June 2002, 4 months after submission. Operator of record: Viridor.
Planning and build timeline
| Application submitted | 11 February 2002 |
| Permission granted | 14 June 2002 4 months after submission |
| Operational | 1 January 2006 43 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Test Valley: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Squabb Wood’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
- Ancient woodland — SQUABB WOOD
- Nutrient-neutrality catchment — Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 1.3 km |
Solar Photovoltaics · Under Construction | — | 3.1 km |
Solar Photovoltaics · Under Construction | 46 | 3.1 km |
Solar Photovoltaics · Operational | 5 | 4.5 km |
Solar Photovoltaics · Operational | 11 | 4.5 km |
Battery · Under Construction | 20 | 6.1 km |
Solar Photovoltaics · Operational | 1.9 | 6.9 km |
Solar Photovoltaics · Operational | 6.4 | 9.5 km |
How big is Squabb Wood?
Squabb Wood has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Squabb Wood?
REPD records the operator as Viridor. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Squabb Wood approved and built?
The application was submitted on 11 February 2002. Permission was granted on 14 June 2002, 4 months later. The site became operational on 1 January 2006, 43 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 644.