Renewable sitesGrove Solar Park (Phase 2)

Grove Solar Park (Phase 2)

Grove Solar Park (Phase 2) is an operational 11 MW solar farm in Test Valley, generating since 30 March 2016. Planning permission was granted on 4 September 2015, 13 months after submission. Operator of record: Solar Century.

11 MW
Capacity
as recorded in REPD
Operational
Status
since 30 March 2016
Solar Photovoltaics
Technology
Solar Century
Test Valley
Authority
England

Planning and build timeline

Application submitted31 July 2014
Permission granted4 September 2015
13 months after submission
Operational30 March 2016
7 months after consent

Screening a site of your own?

RedlineUK · £39

Test Valley approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Grove Solar Park (Phase 2)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Test Valley’s record on solar

Test Valley has decided 37 solar farms and approved 95%, taking a median of 5 months. See every solar farm decision in Test Valley

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50 km
Battery · Under Construction
202.7 km
Solar Photovoltaics · Operational
53.5 km
Solar Photovoltaics · Operational
1.93.7 km
Landfill Gas · Operational
14.5 km
Solar Photovoltaics · Under Construction
6.7 km
Solar Photovoltaics · Under Construction
466.7 km
EfW Incineration · Operational
167.5 km

How big is Grove Solar Park (Phase 2)?

Grove Solar Park (Phase 2) has a recorded installed capacity of 11 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Grove Solar Park (Phase 2)?

REPD records the operator as Solar Century. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Grove Solar Park (Phase 2) approved and built?

The application was submitted on 31 July 2014. Permission was granted on 4 September 2015, 13 months later. The site became operational on 30 March 2016, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6163.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode