Novarly ParcelRenewable sites

Renewable sitesGrove Solar Park (Phase 2)

Grove Solar Park (Phase 2)

Grove Solar Park (Phase 2) is operational in Test Valley with a recorded capacity of 11 MW, and has been generating since 2016-03-30.

11 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-30
Solar Photovoltaics
Technology
Solar Century
Test Valley
Authority
England

Planning and build timeline

Application submitted2014-07-31
Permission granted2015-09-04
13 months after submission
Operational2016-03-30
7 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Test Valley’s record on solar

Test Valley has decided 37 solar farms and approved 95%, taking a median of 5 months. See every solar farm decision in Test Valley

Other built sites within 15 km

SiteMWDistance
Grove Solar Park (Phase 1)
Solar Photovoltaics · Operational
50 km
Mill Lane, Nursling - Battery Storage Facility
Battery · Under Construction
202.7 km
Highwood Lane
Solar Photovoltaics · Operational
53.5 km
Testwood Water Supply Works
Solar Photovoltaics · Operational
1.93.7 km
Squabb Wood
Landfill Gas · Operational
14.5 km
Woodington Solar Farm
Solar Photovoltaics · Under Construction
466.7 km
Woodington Solar Farm (Central)
Solar Photovoltaics · Under Construction
6.7 km
Marchwood ERF
EfW Incineration · Operational
167.5 km

How big is Grove Solar Park (Phase 2)?

Grove Solar Park (Phase 2) has a recorded installed capacity of 11 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Grove Solar Park (Phase 2)?

REPD records the operator as Solar Century. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Grove Solar Park (Phase 2) approved and built?

The application was submitted on 2014-07-31. Permission was granted on 2015-09-04, 13 months later. The site became operational on 2016-03-30, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6163.

Novarly Parcel · official public data, read properly · parcel.novarly.com