Wilmingham Lane Solar Farm
Wilmingham Lane Solar Farm is an operational 7 MW solar farm in Isle of Wight, generating since 14 March 2013. Planning permission was granted on 12 April 2012, 2 months after submission. Operator of record: Low Carbon Solar.
Planning and build timeline
| Application submitted | 27 January 2012 |
| Permission granted | 12 April 2012 2 months after submission |
| Operational | 14 March 2013 11 months after consent |
Screening a site of your own?
Isle of Wight approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Wilmingham Lane Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Nutrient-neutrality catchment — Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Isle of Wight’s record on solar
Isle of Wight has decided 16 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in Isle of Wight →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 2.6 km |
Solar Photovoltaics · Operational | 10.7 | 3.1 km |
Solar Photovoltaics · Operational | 1.5 | 4.6 km |
Solar Photovoltaics · Operational | 2.7 | 7.6 km |
Solar Photovoltaics · Operational | 1.2 | 7.9 km |
Solar Photovoltaics · Operational | 4.5 | 8.8 km |
Landfill Gas · Operational | 1.5 | 8.9 km |
Advanced Conversion Technologies · Under Construction | 3.3 | 10.9 km |
How big is Wilmingham Lane Solar Farm?
Wilmingham Lane Solar Farm has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wilmingham Lane Solar Farm?
REPD records the operator as Low Carbon Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wilmingham Lane Solar Farm approved and built?
The application was submitted on 27 January 2012. Permission was granted on 12 April 2012, 2 months later. The site became operational on 14 March 2013, 11 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1343.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode