Wilmingham Lane Solar Farm

Wilmingham Lane Solar Farm is an operational 7 MW solar farm in Isle of Wight, generating since 14 March 2013. Planning permission was granted on 12 April 2012, 2 months after submission. Operator of record: Low Carbon Solar.

7 MW
Capacity
as recorded in REPD
Operational
Status
since 14 March 2013
Solar Photovoltaics
Technology
Low Carbon Solar
Isle of Wight
Authority
England

Planning and build timeline

Application submitted27 January 2012
Permission granted12 April 2012
2 months after submission
Operational14 March 2013
11 months after consent

Screening a site of your own?

RedlineUK · £39

Isle of Wight approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Wilmingham Lane Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Isle of Wight’s record on solar

Isle of Wight has decided 16 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in Isle of Wight

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
52.6 km
Solar Photovoltaics · Operational
10.73.1 km
Solar Photovoltaics · Operational
1.54.6 km
Solar Photovoltaics · Operational
2.77.6 km
Solar Photovoltaics · Operational
1.27.9 km
Solar Photovoltaics · Operational
4.58.8 km
Landfill Gas · Operational
1.58.9 km
Advanced Conversion Technologies · Under Construction
3.310.9 km

How big is Wilmingham Lane Solar Farm?

Wilmingham Lane Solar Farm has a recorded installed capacity of 7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wilmingham Lane Solar Farm?

REPD records the operator as Low Carbon Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wilmingham Lane Solar Farm approved and built?

The application was submitted on 27 January 2012. Permission was granted on 12 April 2012, 2 months later. The site became operational on 14 March 2013, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1343.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode