Solar planning in Isle of Wight

Isle of Wight has decided 16 solar farms and approved 100% of them, taking a median of 2.7 months to decide. Consented capacity: 124 MW. 2 applications still awaiting a decision.

100%
Approved
16 granted · 0 refused
2.7 mo
Median decision
UK 2.3 mo
124 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Isle of Wight compares

Against the 298 UK authorities with 5+ solar decisions, Isle of Wight sits in the 77th percentile for approval rate (7 points above the England average) and the 42nd percentile for speed.

Decisions by year

35Approved — 3 (2011)311Approved — 4 (2012)412Approved — 2 (2013)213Approved — 3 (2014)314Approved — 2 (2023)223Approved — 2 (2025)225
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (18)

SchemeMWStatusDecided
The Island Free School, Newport Road - Solar Array
The Island Community School T/A The Island · 25/01599/14JPA · 1.3 mo to decide
0.22Awaiting Construction2025-12-10
Sunny Oaks Renewable Energy Park
Ridge Clean Energy Limited · 22/01585/FUL · 34.3 mo to decide
20Awaiting Construction2025-07-15
Bae Systems, Newport Road - Solar Panels
BAE Systems · 25/00169/FUL
0.3Application Submitted2025-02-06
Gkn & Whippingham Technology Park, Beatrice Avenue - Solar Panels
GKN Aerospace Services Limited · 23/00630/FUL · 5.8 mo to decide
1.3Awaiting Construction2023-10-19
Barnfield Solar Farm, Wilmingham Lane - Solar PV Panels
Low Carbon UK Solar · 22/01793/FUL · 11.1 mo to decide
30Awaiting Construction2023-09-08
Morrisons Supermarket, South Street - Solar Photovoltaics
Morrisons · 22/01952/14JPA
0.41Application Submitted2022-10-28
Fieldscale
SBC Renewables · P/00979/14 · 2.5 mo to decide
10.6Operational2014-10-22
Homestead Farm
Anesco · P/00607/14 · 5.1 mo to decide
10.7Operational2014-10-21
Grange Farm
INRG Solar · P/00343/14 · 3 mo to decide
6Operational2014-06-19
East Fairlee
The Solar Building Company Ltd · P/00737/13 · 4.1 mo to decide
7.3Operational2013-10-17
Hill Farm Solar Park
Lightsource Renewable Energy (BNRG Renewables) · P/01485/12 · 3.8 mo to decide
10.2Operational2013-01-29
VENTNOR ROAD SOLAR PARK
BNRG Renewables · P/01484/12 · 2.4 mo to decide
4.8Operational2012-12-21
Chawton Farm Solar Farm
BNRG Renewables · P/01483/12 · 2.4 mo to decide
3.2Operational2012-12-17
Stables Farm
Lightsource Renewable Energy · P/00353/12 · 3 mo to decide
1.5Operational2012-06-12
Wilmingham Lane Solar Farm
Low Carbon Solar · P/00053/12 · 2.5 mo to decide
7Operational2012-04-12
Newnham Farm
Low Carbon Solar (Liquidated) · P/00338/11 · 2 mo to decide
2Planning Permission Expired2011-05-20
Lee Farm
Vogt Solar · P/00168/11 · 2.2 mo to decide
5Operational2011-04-14
Durrants Farm Solar
Kronos Solar/Vogt Solar · P/01901/10 · 2.5 mo to decide
4.5Operational2011-02-28

Does Isle of Wight approve solar farms?

Yes — of the 16 solar farms Isle of Wight has decided, 100% were approved (16 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Isle of Wight?

The median time from application to decision is 2.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Isle of Wight consented?

124 MW has been consented across 16 approved schemes. A further 2 applications awaits a decision.

Other technologies in Isle of Wight

Battery storage in Isle of WightOnshore wind in Isle of Wight

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com