Novarly ParcelRenewable sites

Renewable sitesStanden Heath

Standen Heath

Standen Heath is operational in Isle of Wight with a recorded capacity of 1.5 MW, and has been generating since 2010-03-28.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-03-28
Landfill Gas
Technology
Biffa
Isle of Wight
Authority
England

Planning and build timeline

Application submitted2003-06-02
Permission granted2007-01-30
44 months after submission
Operational2010-03-28
38 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Durrants Farm Solar
Solar Photovoltaics · Operational
4.52.1 km
Isle of Wight Waste Recovery Park
Advanced Conversion Technologies · Under Construction
3.32.3 km
Stables Farm
Solar Photovoltaics · Operational
1.54.5 km
Homestead Farm
Solar Photovoltaics · Operational
10.75.9 km
Greenhill Anaerobic Digestion Plant
Anaerobic Digestion · Operational
16 km
Chawton Farm Solar Farm
Solar Photovoltaics · Operational
3.26.3 km
Lee Farm
Solar Photovoltaics · Operational
56.3 km
Grange Farm
Solar Photovoltaics · Operational
67.4 km

How big is Standen Heath?

Standen Heath has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Standen Heath?

REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Standen Heath approved and built?

The application was submitted on 2003-06-02. Permission was granted on 2007-01-30, 44 months later. The site became operational on 2010-03-28, 38 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 777.