Durrants Farm Solar

Durrants Farm Solar is operational in Isle of Wight with a recorded capacity of 4.5 MW, and has been generating since 2011-07-01.

4.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2011-07-01
Solar Photovoltaics
Technology
Kronos Solar/Vogt Solar
Isle of Wight
Authority
England

Planning and build timeline

Application submitted2010-12-14
Permission granted2011-02-28
2 months after submission
Operational2011-07-01
4 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Isle of Wight’s record on solar

Isle of Wight has decided 16 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in Isle of Wight

Other built sites within 15 km

SiteMWDistance
Standen Heath
Landfill Gas · Operational
1.52.1 km
Isle of Wight Waste Recovery Park
Advanced Conversion Technologies · Under Construction
3.32.4 km
Stables Farm
Solar Photovoltaics · Operational
1.54.2 km
Chawton Farm Solar Farm
Solar Photovoltaics · Operational
3.25.3 km
Greenhill Anaerobic Digestion Plant
Anaerobic Digestion · Operational
15.6 km
Homestead Farm
Solar Photovoltaics · Operational
10.75.7 km
Lee Farm
Solar Photovoltaics · Operational
56.2 km
Grange Farm
Solar Photovoltaics · Operational
67.5 km

How big is Durrants Farm Solar?

Durrants Farm Solar has a recorded installed capacity of 4.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Durrants Farm Solar?

REPD records the operator as Kronos Solar/Vogt Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Durrants Farm Solar approved and built?

The application was submitted on 2010-12-14. Permission was granted on 2011-02-28, 2 months later. The site became operational on 2011-07-01, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1082.