Lee Farm is operational in Isle of Wight with a recorded capacity of 5 MW, and has been generating since 2012-07-31.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-07-31
Solar Photovoltaics
Technology
Vogt Solar
Isle of Wight
Authority
England

Planning and build timeline

Application submitted2011-02-07
Permission granted2011-04-14
2 months after submission
Operational2012-07-31
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Isle of Wight’s record on solar

Isle of Wight has decided 16 solar farms and approved 100%, taking a median of 2.7 months. See every solar farm decision in Isle of Wight

Other built sites within 15 km

SiteMWDistance
Homestead Farm
Solar Photovoltaics · Operational
10.70.5 km
Stables Farm
Solar Photovoltaics · Operational
1.52 km
Wilmingham Lane Solar Farm
Solar Photovoltaics · Operational
72.6 km
Durrants Farm Solar
Solar Photovoltaics · Operational
4.56.2 km
Standen Heath
Landfill Gas · Operational
1.56.3 km
Isle of Wight Waste Recovery Park
Advanced Conversion Technologies · Under Construction
3.38.3 km
Lower Pennington Farm
Solar Photovoltaics · Operational
2.79 km
Pennington Recycling Centre
Solar Photovoltaics · Operational
1.29.6 km

How big is Lee Farm?

Lee Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Lee Farm?

REPD records the operator as Vogt Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Lee Farm approved and built?

The application was submitted on 2011-02-07. Permission was granted on 2011-04-14, 2 months later. The site became operational on 2012-07-31, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1558.