Renewable sites › Willow Farm
Willow Farm
Willow Farm is operational in Fenland with a recorded capacity of 1.15 MW, and has been generating since 2022-08-15.
Planning and build timeline
| Application submitted | 2021-01-13 |
| Permission granted | 2021-11-12 10 months after submission |
| Operational | 2022-08-15 9 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Fenland’s record on solar
Fenland has decided 22 solar farms and approved 91%, taking a median of 2.8 months. See every solar farm decision in Fenland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Colony Farm Anaerobic Digestion · Under Construction | 4 | 3.2 km |
Mepal CHP Anaerobic Digestion · Operational | 14.4 | 9.8 km |
Asksham Community Village Solar Farm Solar Photovoltaics · Under Construction | 0.15 | 10 km |
Stags Holt Extension Wind Onshore · Operational | 2 | 10.4 km |
Stags Holt Wind Onshore · Operational | 18 | 10.4 km |
Boardinghouse Wind Farm Wind Onshore · Operational | 10.3 | 10.5 km |
MARCH SEWAGE TREATMENT WORKS - WIND TURBINE Wind Onshore · Operational | 2 | 10.6 km |
Elean Business Park Biomass Plant Biomass (dedicated) · Operational | 40 | 10.9 km |
How big is Willow Farm?
Willow Farm has a recorded installed capacity of 1.15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Willow Farm?
REPD records the operator as BeBa Energy UK Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Willow Farm approved and built?
The application was submitted on 2021-01-13. Permission was granted on 2021-11-12, 10 months later. The site became operational on 2022-08-15, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8408.