Renewable sitesColony Farm

Colony Farm

Colony Farm is a 4 MW anaerobic digestion plant under construction in Fenland. Planning permission was granted on 21 December 2018, 3 months after submission. Operator of record: Private Developer.

4 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Anaerobic Digestion
Technology
Private Developer
Fenland
Authority
England

Planning and build timeline

Application submitted5 October 2018
Permission granted21 December 2018
3 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Fenland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Colony Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.153.2 km
Wind Onshore · Operational
188.5 km
Wind Onshore · Operational
28.5 km
Wind Onshore · Operational
28.7 km
Wind Onshore · Operational
149.9 km
Wind Onshore · Operational
10.310.4 km
Wind Onshore · Operational
210.5 km
Solar Photovoltaics · Under Construction
0.1511 km

How big is Colony Farm?

Colony Farm has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Colony Farm?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Colony Farm approved and built?

The application was submitted on 5 October 2018. Permission was granted on 21 December 2018, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6824.