Novarly ParcelRenewable sites

Renewable sitesStags Holt Extension

Stags Holt Extension

Stags Holt Extension is operational in Fenland with a recorded capacity of 2 MW, and has been generating since 2010-12-31.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-12-31
Wind Onshore
Technology
E.ON UK
Fenland
Authority
England

Planning and build timeline

Application submitted2007-06-04
Permission granted2008-10-07
16 months after submission
Operational2010-12-31
27 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fenland’s record on onshore wind

Fenland has decided 20 onshore wind schemes and approved 85%, taking a median of 12.8 months. See every onshore wind scheme decision in Fenland

Other built sites within 15 km

SiteMWDistance
Stags Holt
Wind Onshore · Operational
180 km
MARCH SEWAGE TREATMENT WORKS - WIND TURBINE
Wind Onshore · Operational
20.2 km
Long Hill Road
Wind Onshore · Operational
22.3 km
Whitemill Wind Farm
Wind Onshore · Operational
142.8 km
Coldham
Wind Onshore · Operational
163.6 km
Coldham Hall
Wind Onshore · Operational
143.7 km
Fenmarc Fenland AD Plant (Waste AD)
Anaerobic Digestion · Operational
1.54.2 km
Boardinghouse Wind Farm
Wind Onshore · Operational
10.35.7 km

How big is Stags Holt Extension?

Stags Holt Extension has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stags Holt Extension?

REPD records the operator as E.ON UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stags Holt Extension approved and built?

The application was submitted on 2007-06-04. Permission was granted on 2008-10-07, 16 months later. The site became operational on 2010-12-31, 27 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3741.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council