Whitehills Energy Storage Facility is under construction in Angus with a recorded capacity of 49.9 MW.

49.9 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Gigabox Developments Limited / Whirlwind Renewables
Angus
Authority
Scotland

Planning and build timeline

Application submitted2021-07-07
Permission granted2021-12-15
5 months after submission
Operationalnot recorded

Angus’s record on battery storage

Angus has decided 18 battery storage schemes and approved 94%, taking a median of 6.2 months. See every battery storage scheme decision in Angus

Other built sites within 15 km

SiteMWDistance
Lochhead Landfill Scheme
Landfill Gas · Operational
21.9 km
Dragonhall Farm, Padanaram - Solar Photovoltaic Array
Solar Photovoltaics · Under Construction
54.2 km
Dragonhall Farm, Padanaram - Battery Storage
Battery · Under Construction
104.2 km
Pressock Farm
Solar Photovoltaics · Operational
510.4 km
New Mains Of Guynd Farm
Solar Photovoltaics · Operational
1013.3 km
Ark Hill
Wind Onshore · Operational
6.414.3 km

How big is Whitehills Energy Storage Facility?

Whitehills Energy Storage Facility has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Whitehills Energy Storage Facility?

REPD records the operator as Gigabox Developments Limited / Whirlwind Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Whitehills Energy Storage Facility approved and built?

The application was submitted on 2021-07-07. Permission was granted on 2021-12-15, 5 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8916.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council