Whitehills Energy Storage Facility is under construction in Angus with a recorded capacity of 49.9 MW.
Planning and build timeline
| Application submitted | 2021-07-07 |
| Permission granted | 2021-12-15 5 months after submission |
| Operational | not recorded |
Angus’s record on battery storage
Angus has decided 18 battery storage schemes and approved 94%, taking a median of 6.2 months. See every battery storage scheme decision in Angus →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lochhead Landfill Scheme Landfill Gas · Operational | 2 | 1.9 km |
Dragonhall Farm, Padanaram - Solar Photovoltaic Array Solar Photovoltaics · Under Construction | 5 | 4.2 km |
Dragonhall Farm, Padanaram - Battery Storage Battery · Under Construction | 10 | 4.2 km |
Pressock Farm Solar Photovoltaics · Operational | 5 | 10.4 km |
New Mains Of Guynd Farm Solar Photovoltaics · Operational | 10 | 13.3 km |
Ark Hill Wind Onshore · Operational | 6.4 | 14.3 km |
How big is Whitehills Energy Storage Facility?
Whitehills Energy Storage Facility has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Whitehills Energy Storage Facility?
REPD records the operator as Gigabox Developments Limited / Whirlwind Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Whitehills Energy Storage Facility approved and built?
The application was submitted on 2021-07-07. Permission was granted on 2021-12-15, 5 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8916.