Renewable sites › Dragonhall Farm, Padanaram - Solar Photovoltaic Array
Dragonhall Farm, Padanaram - Solar Photovoltaic Array
Dragonhall Farm, Padanaram - Solar Photovoltaic Array is a 5 MW solar farm under construction in Angus. Planning permission was granted on 22 September 2021, 4 months after submission. Operator of record: Ecosse Solar Parks Limited.
Planning and build timeline
| Application submitted | 12 May 2021 |
| Permission granted | 22 September 2021 4 months after submission |
| Operational | not recorded |
Screening a site of your own?
Angus approves 97% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Dragonhall Farm, Padanaram - Solar Photovoltaic Array’s recorded coordinate — swap in your own postcode or coordinates.
Angus’s record on solar
Angus has decided 30 solar farms and approved 97%, taking a median of 4 months. See every solar farm decision in Angus →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | 10 | 0 km |
Battery · Under Construction | 49.9 | 4.2 km |
Landfill Gas · Operational | 2 | 6.1 km |
Wind Onshore · Operational | 6.4 | 11.4 km |
Solar Photovoltaics · Operational | 5 | 14.6 km |
How big is Dragonhall Farm, Padanaram - Solar Photovoltaic Array?
Dragonhall Farm, Padanaram - Solar Photovoltaic Array has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dragonhall Farm, Padanaram - Solar Photovoltaic Array?
REPD records the operator as Ecosse Solar Parks Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dragonhall Farm, Padanaram - Solar Photovoltaic Array approved and built?
The application was submitted on 12 May 2021. Permission was granted on 22 September 2021, 4 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9065.