City Football Academy, Ashton New Road - Solar panels is under construction in Manchester with a recorded capacity of 3.38 MW.

3.38 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Manchester City Football Club
Manchester
Authority
England

Planning and build timeline

Application submitted2024-03-14
Permission granted2024-04-26
1 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Manchester’s record on solar

Manchester has decided 45 solar farms and approved 91%, taking a median of 1.7 months. See every solar farm decision in Manchester

Other built sites within 15 km

SiteMWDistance
The National Cycling Centre Velodrome
Solar Photovoltaics · Operational
0.70.5 km
The National Cycling Centre - Solar Photovoltaic Panels
Solar Photovoltaics · Under Construction
0.920.5 km
Ardwick Railway Goods Yard Incinerator (Newhaven EFW Plant)
EfW Incineration · Operational
33.51.3 km
Outer Space Studios Solar Panels
Solar Photovoltaics · Operational
0.61.4 km
Central Park - Solar photovaltics
Solar Photovoltaics · Operational
0.152.4 km
Tesco Super-Store (Garratt Way, Gorton)
Solar Photovoltaics · Operational
0.72.5 km
Reliance Street Mechanical Biological Treatment Facility (MBT)
Anaerobic Digestion · Operational
22.7 km
Moston Vale
Battery · Under Construction
102.8 km

How big is City Football Academy, Ashton New Road - Solar panels?

City Football Academy, Ashton New Road - Solar panels has a recorded installed capacity of 3.38 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates City Football Academy, Ashton New Road - Solar panels?

REPD records the operator as Manchester City Football Club. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was City Football Academy, Ashton New Road - Solar panels approved and built?

The application was submitted on 2024-03-14. Permission was granted on 2024-04-26, 1 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 16119.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council