Planning and build timeline
| Application submitted | 2021-06-24 |
| Permission granted | 2021-09-15 3 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Manchester’s record on solar
Manchester has decided 45 solar farms and approved 91%, taking a median of 1.7 months. See every solar farm decision in Manchester →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Moston Vale Battery · Under Construction | 10 | 0.5 km |
Reliance Street Mechanical Biological Treatment Facility (MBT) Anaerobic Digestion · Operational | 2 | 1.5 km |
The National Cycling Centre Velodrome Solar Photovoltaics · Operational | 0.7 | 2 km |
The National Cycling Centre - Solar Photovoltaic Panels Solar Photovoltaics · Under Construction | 0.92 | 2.1 km |
City Football Academy, Ashton New Road - Solar panels Solar Photovoltaics · Under Construction | 3.38 | 2.4 km |
Ardwick Railway Goods Yard Incinerator (Newhaven EFW Plant) EfW Incineration · Operational | 33.5 | 3.2 km |
Land at Wrigley Head Solar Photovoltaics · Under Construction | 0.9 | 3.5 km |
Outer Space Studios Solar Panels Solar Photovoltaics · Operational | 0.6 | 3.7 km |
How big is Central Park - Solar photovaltics?
Central Park - Solar photovaltics has a recorded installed capacity of 0.15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Central Park - Solar photovaltics?
REPD records the operator as Greater Manchester Police. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Central Park - Solar photovaltics approved and built?
The application was submitted on 2021-06-24. Permission was granted on 2021-09-15, 3 months later. REPD does not record an operational date.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9272.