The National Cycling Centre Velodrome

The National Cycling Centre Velodrome is an operational 0.7 MW solar farm in Manchester, generating since 1 July 2023. Planning permission was granted on 30 October 2020, 2 months after submission. Operator of record: Manchester City Council.

0.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2023
Solar Photovoltaics
Technology
Manchester City Council
Manchester
Authority
England

Planning and build timeline

Application submitted7 September 2020
Permission granted30 October 2020
2 months after submission
Operational1 July 2023
32 months after consent

Screening a site of your own?

RedlineUK · £39

Manchester approves 91% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with The National Cycling Centre Velodrome’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Manchester’s record on solar

Manchester has decided 45 solar farms and approved 91%, taking a median of 1.7 months. See every solar farm decision in Manchester

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
0.920.1 km
Solar Photovoltaics · Under Construction
3.380.5 km
EfW Incineration · Operational
33.51.7 km
Solar Photovoltaics · Operational
0.61.9 km
Solar Photovoltaics · Operational
0.152 km
Anaerobic Digestion · Operational
22.2 km
Battery · Under Construction
102.4 km
Solar Photovoltaics · Operational
0.72.9 km

How big is The National Cycling Centre Velodrome?

The National Cycling Centre Velodrome has a recorded installed capacity of 0.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates The National Cycling Centre Velodrome?

REPD records the operator as Manchester City Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was The National Cycling Centre Velodrome approved and built?

The application was submitted on 7 September 2020. Permission was granted on 30 October 2020, 2 months later. The site became operational on 1 July 2023, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8030.