Renewable sites › Greatmoor EfW
Greatmoor EfW
Greatmoor EfW is an operational 22 MW energy-from-waste plant in Buckinghamshire, generating since 23 February 2016. Planning permission was granted on 26 July 2012, 17 months after submission. Operator of record: FCC Environment.
Planning and build timeline
| Application submitted | 18 February 2011 |
| Permission granted | 26 July 2012 17 months after submission |
| Operational | 23 February 2016 43 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Buckinghamshire: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Greatmoor EfW’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 11.2 | 1.6 km |
Anaerobic Digestion · Operational | 2 | 7.3 km |
Solar Photovoltaics · Operational | 1.3 | 8.2 km |
Solar Photovoltaics · Operational | 9.2 | 8.3 km |
Solar Photovoltaics · Operational | 0.2 | 8.4 km |
Solar Photovoltaics · Operational | 22 | 8.6 km |
Battery · Operational | — | 8.8 km |
Solar Photovoltaics · Operational | 5 | 10.4 km |
How big is Greatmoor EfW?
Greatmoor EfW has a recorded installed capacity of 22 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Greatmoor EfW?
REPD records the operator as FCC Environment. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Greatmoor EfW approved and built?
The application was submitted on 18 February 2011. Permission was granted on 26 July 2012, 17 months later. The site became operational on 23 February 2016, 43 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 968.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode