West Mill is operational in Uttlesford with a recorded capacity of 2.5 MW, and has been generating since 2005-03-01.

2.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2005-03-01
Landfill Gas
Technology
RMC Aggregates
Uttlesford
Authority
England

Planning and build timeline

Application submitted1999-04-22
Permission granted1999-07-19
3 months after submission
Operational2005-03-01
67 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Stanstead Solar Project
Solar Photovoltaics · Under Construction
14.31.7 km
Ugley
Landfill Gas · Operational
1.15.9 km
Station Works AD
Anaerobic Digestion · Operational
19.3 km
Dunmow Solar Farm, Chelmsford Road - Solar Farm
Solar Photovoltaics · Under Construction
9.899.7 km
Pelham
Battery · Operational
4910.3 km
Tooleys Farm
Solar Photovoltaics · Operational
5.310.5 km
The Nurseries, Green Tye
Anaerobic Digestion · Operational
1.211.1 km
Terriers Farm
Solar Photovoltaics · Operational
4412.2 km

How big is West Mill?

West Mill has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates West Mill?

REPD records the operator as RMC Aggregates. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was West Mill approved and built?

The application was submitted on 1999-04-22. Permission was granted on 1999-07-19, 3 months later. The site became operational on 2005-03-01, 67 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 679.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council