Novarly ParcelRenewable sites

Renewable sitesWest Mill

West Mill

West Mill is an operational 2.5 MW landfill gas site in Uttlesford, generating since 1 March 2005. Planning permission was granted on 19 July 1999, 3 months after submission. Operator of record: RMC Aggregates.

2.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 March 2005
Landfill Gas
Technology
RMC Aggregates
Uttlesford
Authority
England

Planning and build timeline

Application submitted22 April 1999
Permission granted19 July 1999
3 months after submission
Operational1 March 2005
67 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Uttlesford: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with West Mill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
14.31.7 km
Landfill Gas · Operational
1.15.9 km
Anaerobic Digestion · Operational
19.3 km
Solar Photovoltaics · Under Construction
9.899.7 km
Battery · Operational
4910.3 km
Solar Photovoltaics · Operational
5.310.5 km
Anaerobic Digestion · Operational
1.211.1 km
Solar Photovoltaics · Operational
4412.2 km

How big is West Mill?

West Mill has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates West Mill?

REPD records the operator as RMC Aggregates. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was West Mill approved and built?

The application was submitted on 22 April 1999. Permission was granted on 19 July 1999, 3 months later. The site became operational on 1 March 2005, 67 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 679.