West Didsbury Battery Storage

West Didsbury Battery Storage is an operational 49.99 MW battery storage site in Trafford, generating since 21 November 2023. Planning permission was granted on 22 November 2019, 26 months after submission. Operator of record: Statera Energy / Gresham House.

49.99 MW
Capacity
as recorded in REPD
Operational
Status
since 21 November 2023
Battery
Technology
Statera Energy / Gresham House
Trafford
Authority
England

Planning and build timeline

Application submitted25 September 2017
Permission granted22 November 2019
26 months after submission
Operational21 November 2023
48 months after consent

Screening a site of your own?

RedlineUK · £39

Trafford approves 89% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with West Didsbury Battery Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Trafford’s record on battery storage

Trafford has decided 9 battery storage schemes and approved 89%, taking a median of 7.4 months. See every battery storage scheme decision in Trafford

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
99.90.1 km
Anaerobic Digestion · Operational
23.6 km
Solar Photovoltaics · Under Construction
0.55.8 km
Solar Photovoltaics · Under Construction
0.176.3 km
Solar Photovoltaics · Operational
0.277.2 km
Solar Photovoltaics · Under Construction
0.487.4 km
Solar Photovoltaics · Operational
0.67.8 km
EfW Incineration · Operational
33.57.8 km

How big is West Didsbury Battery Storage?

West Didsbury Battery Storage has a recorded installed capacity of 49.99 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates West Didsbury Battery Storage?

REPD records the operator as Statera Energy / Gresham House. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was West Didsbury Battery Storage approved and built?

The application was submitted on 25 September 2017. Permission was granted on 22 November 2019, 26 months later. The site became operational on 21 November 2023, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7185.