Novarly ParcelRenewable sites

Renewable sitesSouth Manchester Resource Recovery Centre (AD)

South Manchester Resource Recovery Centre (AD)

South Manchester Resource Recovery Centre (AD) is operational in Manchester with a recorded capacity of 2 MW, and has been generating since 2012-01-01.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-01-01
Anaerobic Digestion
Technology
Viridor
Manchester
Authority
England

Planning and build timeline

Application submitted2007-07-23
Permission granted2007-12-20
5 months after submission
Operational2012-01-01
48 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
West Didsbury Battery Storage
Battery · Operational
49.993.6 km
Freshfields, Fairy Lane - Battery Storage
Battery · Under Construction
99.93.7 km
Audi Stockport, Brinksway, Edgeley - Solar Panels
Solar Photovoltaics · Operational
0.275 km
Tesco Extra Altrincham
Solar Photovoltaics · Under Construction
0.56.8 km
Welkin Road, Bredbury - Battery Storage System
Battery · Operational
207.7 km
Welkin Mill, Welkin Road - Battery Storage
Battery · Under Construction
49.97.7 km
Bredbury Substation - Battery Storage Facility
Battery · Under Construction
49.97.8 km
Royal Northern College Of Music, Oxford Road - Solar Photovoltaic panels
Solar Photovoltaics · Under Construction
0.178.3 km

How big is South Manchester Resource Recovery Centre (AD)?

South Manchester Resource Recovery Centre (AD) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates South Manchester Resource Recovery Centre (AD)?

REPD records the operator as Viridor. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was South Manchester Resource Recovery Centre (AD) approved and built?

The application was submitted on 2007-07-23. Permission was granted on 2007-12-20, 5 months later. The site became operational on 2012-01-01, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 217.

Novarly Parcel · official public data, read properly · parcel.novarly.com