Novarly ParcelRenewable sites

Renewable sitesWern Ddu Wind Farm

Wern Ddu Wind Farm

Wern Ddu Wind Farm is operational in Denbighshire with a recorded capacity of 9.2 MW, and has been generating since 2010-03-01.

9.2 MW
Capacity
as recorded in REPD
Operational
Status
since 2010-03-01
Wind Onshore
Technology
Tegni
Denbighshire
Authority
Wales

Planning and build timeline

Application submitted2004-04-23
Permission granted2005-01-26
9 months after submission
Operational2010-03-01
61 months after consent

Denbighshire’s record on onshore wind

Denbighshire has decided 5 onshore wind schemes and approved 80%, taking a median of 11 months. See every onshore wind scheme decision in Denbighshire

Other built sites within 15 km

SiteMWDistance
Rhug Estate
Solar Photovoltaics · Operational
1.25 km
Bodtegir
Wind Onshore · Operational
1.56.3 km
Clocaenog Forest Wind Farm
Wind Onshore · Operational
967.5 km
Brenig Wind Farm
Wind Onshore · Operational
37.611.3 km
Tir Mostyn And Foel Goch Wind Farm
Wind Onshore · Operational
21.311.7 km
Blazer Fuels
Biomass (dedicated) · Operational
312 km
Hafoty Ucha '2' and '3' Wind Turbine
Wind Onshore · Operational
2.612.7 km

How big is Wern Ddu Wind Farm?

Wern Ddu Wind Farm has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wern Ddu Wind Farm?

REPD records the operator as Tegni. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wern Ddu Wind Farm approved and built?

The application was submitted on 2004-04-23. Permission was granted on 2005-01-26, 9 months later. The site became operational on 2010-03-01, 61 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3592.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council