Renewable sites › Wern Ddu Wind Farm
Wern Ddu Wind Farm
Wern Ddu Wind Farm is operational in Denbighshire with a recorded capacity of 9.2 MW, and has been generating since 2010-03-01.
Planning and build timeline
| Application submitted | 2004-04-23 |
| Permission granted | 2005-01-26 9 months after submission |
| Operational | 2010-03-01 61 months after consent |
Denbighshire’s record on onshore wind
Denbighshire has decided 5 onshore wind schemes and approved 80%, taking a median of 11 months. See every onshore wind scheme decision in Denbighshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rhug Estate Solar Photovoltaics · Operational | 1.2 | 5 km |
Bodtegir Wind Onshore · Operational | 1.5 | 6.3 km |
Clocaenog Forest Wind Farm Wind Onshore · Operational | 96 | 7.5 km |
Brenig Wind Farm Wind Onshore · Operational | 37.6 | 11.3 km |
Tir Mostyn And Foel Goch Wind Farm Wind Onshore · Operational | 21.3 | 11.7 km |
Blazer Fuels Biomass (dedicated) · Operational | 3 | 12 km |
Hafoty Ucha '2' and '3' Wind Turbine Wind Onshore · Operational | 2.6 | 12.7 km |
How big is Wern Ddu Wind Farm?
Wern Ddu Wind Farm has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Wern Ddu Wind Farm?
REPD records the operator as Tegni. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Wern Ddu Wind Farm approved and built?
The application was submitted on 2004-04-23. Permission was granted on 2005-01-26, 9 months later. The site became operational on 2010-03-01, 61 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3592.