Clocaenog Forest Wind Farm

Clocaenog Forest Wind Farm is operational in Wales with a recorded capacity of 96 MW, and has been generating since 2019-10-01.

96 MW
Capacity
as recorded in REPD
Operational
Status
since 2019-10-01
Wind Onshore
Technology
RWE Innogy UK
National
Authority
Wales

Planning and build timeline

Application submitted2013-04-23
Permission granted2014-09-12
17 months after submission
Operational2019-10-01
61 months after consent

Other built sites within 15 km

SiteMWDistance
Brenig Wind Farm
Wind Onshore · Operational
37.64.3 km
Tir Mostyn And Foel Goch Wind Farm
Wind Onshore · Operational
21.35.1 km
Bodtegir
Wind Onshore · Operational
1.56 km
Wern Ddu Wind Farm
Wind Onshore · Operational
9.27.5 km
Rhug Estate
Solar Photovoltaics · Operational
1.29.8 km
Hafoty Ucha '2' and '3' Wind Turbine
Wind Onshore · Operational
2.610.7 km
Blazer Fuels
Biomass (dedicated) · Operational
312.5 km

How big is Clocaenog Forest Wind Farm?

Clocaenog Forest Wind Farm has a recorded installed capacity of 96 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Clocaenog Forest Wind Farm?

REPD records the operator as RWE Innogy UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Clocaenog Forest Wind Farm approved and built?

The application was submitted on 2013-04-23. Permission was granted on 2014-09-12, 17 months later. The site became operational on 2019-10-01, 61 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4552.