| Application submitted | 2013-04-23 |
| Permission granted | 2014-09-12 17 months after submission |
| Operational | 2019-10-01 61 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Brenig Wind Farm Wind Onshore · Operational | 37.6 | 4.3 km |
Tir Mostyn And Foel Goch Wind Farm Wind Onshore · Operational | 21.3 | 5.1 km |
Bodtegir Wind Onshore · Operational | 1.5 | 6 km |
Wern Ddu Wind Farm Wind Onshore · Operational | 9.2 | 7.5 km |
Rhug Estate Solar Photovoltaics · Operational | 1.2 | 9.8 km |
Hafoty Ucha '2' and '3' Wind Turbine Wind Onshore · Operational | 2.6 | 10.7 km |
Blazer Fuels Biomass (dedicated) · Operational | 3 | 12.5 km |
How big is Clocaenog Forest Wind Farm?
Clocaenog Forest Wind Farm has a recorded installed capacity of 96 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Clocaenog Forest Wind Farm?
REPD records the operator as RWE Innogy UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Clocaenog Forest Wind Farm approved and built?
The application was submitted on 2013-04-23. Permission was granted on 2014-09-12, 17 months later. The site became operational on 2019-10-01, 61 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4552.