Renewable sites › Tir Mostyn And Foel Goch Wind Farm
Tir Mostyn And Foel Goch Wind Farm
Tir Mostyn And Foel Goch Wind Farm is operational in Denbighshire with a recorded capacity of 21.3 MW, and has been generating since 2005-06-01.
Planning and build timeline
| Application submitted | 1999-09-22 |
| Permission granted | 2002-12-19 39 months after submission |
| Operational | 2005-06-01 29 months after consent |
Denbighshire’s record on onshore wind
Denbighshire has decided 5 onshore wind schemes and approved 80%, taking a median of 11 months. See every onshore wind scheme decision in Denbighshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Brenig Wind Farm Wind Onshore · Operational | 37.6 | 1.2 km |
Clocaenog Forest Wind Farm Wind Onshore · Operational | 96 | 5.1 km |
Bodtegir Wind Onshore · Operational | 1.5 | 11.1 km |
Blazer Fuels Biomass (dedicated) · Operational | 3 | 11.3 km |
Wern Ddu Wind Farm Wind Onshore · Operational | 9.2 | 11.7 km |
Rhug Estate Solar Photovoltaics · Operational | 1.2 | 14.7 km |
Hafoty Ucha '2' and '3' Wind Turbine Wind Onshore · Operational | 2.6 | 14.9 km |
How big is Tir Mostyn And Foel Goch Wind Farm?
Tir Mostyn And Foel Goch Wind Farm has a recorded installed capacity of 21.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tir Mostyn And Foel Goch Wind Farm?
REPD records the operator as Munich Re (previously Windjen Power Ltd). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tir Mostyn And Foel Goch Wind Farm approved and built?
The application was submitted on 1999-09-22. Permission was granted on 2002-12-19, 39 months later. The site became operational on 2005-06-01, 29 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4689.