Bodtegir

Bodtegir is an operational 1.5 MW onshore wind farm in Conwy, generating since 1 November 2017. Planning permission was granted on 20 April 2016, 2 months after submission. Operator of record: Clean Earth Energy.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 November 2017
Wind Onshore
Technology
Clean Earth Energy
Conwy
Authority
Wales

Planning and build timeline

Application submitted12 February 2016
Permission granted20 April 2016
2 months after submission
Operational1 November 2017
18 months after consent

Screening a site of your own?

RedlineUK · £39

Conwy approves 57% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bodtegir’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Conwy’s record on onshore wind

Conwy has decided 7 onshore wind schemes and approved 57%, taking a median of 6.3 months. See every onshore wind scheme decision in Conwy

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.24.9 km
Wind Onshore · Operational
966 km
Wind Onshore · Operational
9.26.3 km
Wind Onshore · Operational
2.66.5 km
Wind Onshore · Operational
37.610.2 km
Wind Onshore · Operational
21.311.1 km
Small Hydro · Operational
4.514.2 km

How big is Bodtegir?

Bodtegir has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bodtegir?

REPD records the operator as Clean Earth Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bodtegir approved and built?

The application was submitted on 12 February 2016. Permission was granted on 20 April 2016, 2 months later. The site became operational on 1 November 2017, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6033.