Renewable sites › Bodtegir
Bodtegir
Bodtegir is operational in Conwy with a recorded capacity of 1.5 MW, and has been generating since 2017-11-01.
Planning and build timeline
| Application submitted | 2016-02-12 |
| Permission granted | 2016-04-20 2 months after submission |
| Operational | 2017-11-01 18 months after consent |
Conwy’s record on onshore wind
Conwy has decided 7 onshore wind schemes and approved 57%, taking a median of 6.3 months. See every onshore wind scheme decision in Conwy →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rhug Estate Solar Photovoltaics · Operational | 1.2 | 4.9 km |
Clocaenog Forest Wind Farm Wind Onshore · Operational | 96 | 6 km |
Wern Ddu Wind Farm Wind Onshore · Operational | 9.2 | 6.3 km |
Hafoty Ucha '2' and '3' Wind Turbine Wind Onshore · Operational | 2.6 | 6.5 km |
Brenig Wind Farm Wind Onshore · Operational | 37.6 | 10.2 km |
Tir Mostyn And Foel Goch Wind Farm Wind Onshore · Operational | 21.3 | 11.1 km |
Llyn Celyn Small Hydro · Operational | 4.5 | 14.2 km |
How big is Bodtegir?
Bodtegir has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bodtegir?
REPD records the operator as Clean Earth Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bodtegir approved and built?
The application was submitted on 2016-02-12. Permission was granted on 2016-04-20, 2 months later. The site became operational on 2017-11-01, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6033.
Novarly Parcel · official public data, read properly · parcel.novarly.com