Hafoty Ucha '2' and '3' Wind Turbine is an operational 2.6 MW onshore wind farm in Conwy, generating since 15 December 2002. Planning permission was granted on 17 October 2001, 4 months after submission. Operator of record: Private Developer.
Planning and build timeline
| Application submitted | 2 July 2001 |
| Permission granted | 17 October 2001 4 months after submission |
| Operational | 15 December 2002 14 months after consent |
Screening a site of your own?
Conwy approves 57% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Hafoty Ucha '2' and '3' Wind Turbine’s recorded coordinate — swap in your own postcode or coordinates.
Conwy’s record on onshore wind
Conwy has decided 7 onshore wind schemes and approved 57%, taking a median of 6.3 months. See every onshore wind scheme decision in Conwy →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 1.5 | 6.5 km |
Small Hydro · Operational | 4.5 | 8.1 km |
Solar Photovoltaics · Operational | 1.2 | 9.7 km |
Wind Onshore · Operational | 96 | 10.7 km |
Wind Onshore · Operational | 9.2 | 12.7 km |
Wind Onshore · Operational | 37.6 | 13.8 km |
Wind Onshore · Operational | 21.3 | 14.9 km |
How big is Hafoty Ucha '2' and '3' Wind Turbine?
Hafoty Ucha '2' and '3' Wind Turbine has a recorded installed capacity of 2.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hafoty Ucha '2' and '3' Wind Turbine?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hafoty Ucha '2' and '3' Wind Turbine approved and built?
The application was submitted on 2 July 2001. Permission was granted on 17 October 2001, 4 months later. The site became operational on 15 December 2002, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2568.
Novarly Parcel · official public data, read properly · parcel.novarly.com