Weldon Phase 1 and 2

Weldon Phase 1 and 2 is operational in North Northamptonshire with a recorded capacity of 4 MW, and has been generating since 2002-06-15.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 2002-06-15
Landfill Gas
Technology
Waste Recycling Group
North Northamptonshire
Authority
England

Planning and build timeline

Application submitted1996-06-05
Permission granted1997-06-12
12 months after submission
Operational2002-06-15
60 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Jacksons Bakery - Solar Panels
Solar Photovoltaics · Under Construction
0.632.8 km
New Albion Wind Farm
Wind Onshore · Operational
14.48.7 km
Colpmans Farm
Solar Photovoltaics · Operational
510.6 km
Gaultney Solar Park
Solar Photovoltaics · Operational
20.511.4 km
Fernbrook AD Plant (Waste AD)
Anaerobic Digestion · Operational
1.511.8 km
Seaton Road Solar Farm
Solar Photovoltaics · Operational
411.9 km
Lilford Hall, Lilford - Solar Panels
Solar Photovoltaics · Under Construction
112 km
Cranford
Landfill Gas · Operational
1.112.3 km

How big is Weldon Phase 1 and 2?

Weldon Phase 1 and 2 has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Weldon Phase 1 and 2?

REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Weldon Phase 1 and 2 approved and built?

The application was submitted on 1996-06-05. Permission was granted on 1997-06-12, 12 months later. The site became operational on 2002-06-15, 60 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 538.