Renewable sites › Weldon Phase 1 and 2
Weldon Phase 1 and 2
Weldon Phase 1 and 2 is operational in North Northamptonshire with a recorded capacity of 4 MW, and has been generating since 2002-06-15.
Planning and build timeline
| Application submitted | 1996-06-05 |
| Permission granted | 1997-06-12 12 months after submission |
| Operational | 2002-06-15 60 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Jacksons Bakery - Solar Panels Solar Photovoltaics · Under Construction | 0.63 | 2.8 km |
New Albion Wind Farm Wind Onshore · Operational | 14.4 | 8.7 km |
Colpmans Farm Solar Photovoltaics · Operational | 5 | 10.6 km |
Gaultney Solar Park Solar Photovoltaics · Operational | 20.5 | 11.4 km |
Fernbrook AD Plant (Waste AD) Anaerobic Digestion · Operational | 1.5 | 11.8 km |
Seaton Road Solar Farm Solar Photovoltaics · Operational | 4 | 11.9 km |
Lilford Hall, Lilford - Solar Panels Solar Photovoltaics · Under Construction | 1 | 12 km |
Cranford Landfill Gas · Operational | 1.1 | 12.3 km |
How big is Weldon Phase 1 and 2?
Weldon Phase 1 and 2 has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Weldon Phase 1 and 2?
REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Weldon Phase 1 and 2 approved and built?
The application was submitted on 1996-06-05. Permission was granted on 1997-06-12, 12 months later. The site became operational on 2002-06-15, 60 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 538.