Jacksons Bakery - Solar Panels is under construction in North Northamptonshire with a recorded capacity of 0.63 MW.

0.63 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Jackson Bakery
North Northamptonshire
Authority
England

Planning and build timeline

Application submitted2021-06-23
Permission granted2022-07-11
13 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Northamptonshire’s record on solar

North Northamptonshire has decided 41 solar farms and approved 98%, taking a median of 2 months. See every solar farm decision in North Northamptonshire

Other built sites within 15 km

SiteMWDistance
Weldon Phase 1 and 2
Landfill Gas · Operational
42.8 km
New Albion Wind Farm
Wind Onshore · Operational
14.47.9 km
Seaton Road Solar Farm
Solar Photovoltaics · Operational
49.6 km
Gaultney Solar Park
Solar Photovoltaics · Operational
20.510.2 km
Fernbrook AD Plant (Waste AD)
Anaerobic Digestion · Operational
1.511.7 km
Eckland Lodge Farm
Solar Photovoltaics · Operational
2.912.3 km
Colpmans Farm
Solar Photovoltaics · Operational
513.2 km
Cranford
Landfill Gas · Operational
1.114.3 km

How big is Jacksons Bakery - Solar Panels?

Jacksons Bakery - Solar Panels has a recorded installed capacity of 0.63 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Jacksons Bakery - Solar Panels?

REPD records the operator as Jackson Bakery. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Jacksons Bakery - Solar Panels approved and built?

The application was submitted on 2021-06-23. Permission was granted on 2022-07-11, 13 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9367.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council