Jacksons Bakery - Solar Panels is a 0.63 MW solar farm under construction in North Northamptonshire. Planning permission was granted on 11 July 2022, 13 months after submission. Operator of record: Jackson Bakery.

0.63 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Jackson Bakery
North Northamptonshire
Authority
England

Planning and build timeline

Application submitted23 June 2021
Permission granted11 July 2022
13 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

North Northamptonshire approves 98% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Jacksons Bakery - Solar Panels’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

North Northamptonshire’s record on solar

North Northamptonshire has decided 41 solar farms and approved 98%, taking a median of 2 months. See every solar farm decision in North Northamptonshire

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
42.8 km
Wind Onshore · Operational
14.47.9 km
Solar Photovoltaics · Operational
49.6 km
Solar Photovoltaics · Operational
20.510.2 km
Anaerobic Digestion · Operational
1.511.7 km
Solar Photovoltaics · Operational
2.912.3 km
Solar Photovoltaics · Operational
513.2 km
Landfill Gas · Operational
1.114.3 km

How big is Jacksons Bakery - Solar Panels?

Jacksons Bakery - Solar Panels has a recorded installed capacity of 0.63 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Jacksons Bakery - Solar Panels?

REPD records the operator as Jackson Bakery. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Jacksons Bakery - Solar Panels approved and built?

The application was submitted on 23 June 2021. Permission was granted on 11 July 2022, 13 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9367.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode