Jacksons Bakery - Solar Panels is under construction in North Northamptonshire with a recorded capacity of 0.63 MW.
Planning and build timeline
| Application submitted | 2021-06-23 |
| Permission granted | 2022-07-11 13 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
North Northamptonshire’s record on solar
North Northamptonshire has decided 41 solar farms and approved 98%, taking a median of 2 months. See every solar farm decision in North Northamptonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Weldon Phase 1 and 2 Landfill Gas · Operational | 4 | 2.8 km |
New Albion Wind Farm Wind Onshore · Operational | 14.4 | 7.9 km |
Seaton Road Solar Farm Solar Photovoltaics · Operational | 4 | 9.6 km |
Gaultney Solar Park Solar Photovoltaics · Operational | 20.5 | 10.2 km |
Fernbrook AD Plant (Waste AD) Anaerobic Digestion · Operational | 1.5 | 11.7 km |
Eckland Lodge Farm Solar Photovoltaics · Operational | 2.9 | 12.3 km |
Colpmans Farm Solar Photovoltaics · Operational | 5 | 13.2 km |
Cranford Landfill Gas · Operational | 1.1 | 14.3 km |
How big is Jacksons Bakery - Solar Panels?
Jacksons Bakery - Solar Panels has a recorded installed capacity of 0.63 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Jacksons Bakery - Solar Panels?
REPD records the operator as Jackson Bakery. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Jacksons Bakery - Solar Panels approved and built?
The application was submitted on 2021-06-23. Permission was granted on 2022-07-11, 13 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9367.