Bustleholme Substation

Bustleholme Substation is operational in Sandwell with a recorded capacity of 49.9 MW, and has been generating since 2023-10-20.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 2023-10-20
Battery
Technology
Pivot Power
Sandwell
Authority
England

Planning and build timeline

Application submitted2020-07-06
Permission granted2021-02-01
7 months after submission
Operational2023-10-20
33 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Sandwell’s record on battery storage

Sandwell has decided 13 battery storage schemes and approved 92%, taking a median of 2.6 months. See every battery storage scheme decision in Sandwell

Other built sites within 15 km

SiteMWDistance
Wednesbury
EfW Incineration · Under Construction
24.9 km
Golds Hill - Battery Storage
Battery · Operational
575.3 km
Bloxwich Battery
Battery · Operational
415.5 km
Kelvin Energy Recovery Facility
EfW Incineration · Under Construction
475.8 km
Kelvin Energy Recovery Facility
EfW Incineration · Under Construction
475.8 km
DPD Distribution Centre
Solar Photovoltaics · Operational
16.3 km
Oldbury
Advanced Conversion Technologies · Operational
406.3 km
BH Energy Gap - Waste Energy Plant, The 3Rs
EfW Incineration · Under Construction
497.1 km

How big is Bustleholme Substation?

Bustleholme Substation has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bustleholme Substation?

REPD records the operator as Pivot Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bustleholme Substation approved and built?

The application was submitted on 2020-07-06. Permission was granted on 2021-02-01, 7 months later. The site became operational on 2023-10-20, 33 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7907.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council