Bustleholme Substation

Bustleholme Substation is an operational 49.9 MW battery storage site in Sandwell, generating since 20 October 2023. Planning permission was granted on 1 February 2021, 7 months after submission. Operator of record: Pivot Power.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 20 October 2023
Battery
Technology
Pivot Power
Sandwell
Authority
England

Planning and build timeline

Application submitted6 July 2020
Permission granted1 February 2021
7 months after submission
Operational20 October 2023
33 months after consent

Screening a site of your own?

RedlineUK · £39

Sandwell approves 92% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bustleholme Substation’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Sandwell’s record on battery storage

Sandwell has decided 13 battery storage schemes and approved 92%, taking a median of 2.6 months. See every battery storage scheme decision in Sandwell

Other built sites within 15 km

SiteMWDistance
EfW Incineration · Under Construction
24.9 km
Battery · Operational
575.3 km
Battery · Operational
415.5 km
EfW Incineration · Under Construction
475.8 km
EfW Incineration · Under Construction
475.8 km
Solar Photovoltaics · Operational
16.3 km
Advanced Conversion Technologies · Operational
406.3 km
EfW Incineration · Under Construction
497.1 km

How big is Bustleholme Substation?

Bustleholme Substation has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bustleholme Substation?

REPD records the operator as Pivot Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bustleholme Substation approved and built?

The application was submitted on 6 July 2020. Permission was granted on 1 February 2021, 7 months later. The site became operational on 20 October 2023, 33 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7907.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode