Waterloo solar park
Waterloo solar park is operational in Central Bedfordshire with a recorded capacity of 14.6 MW, and has been generating since 2015-03-19.
Planning and build timeline
| Application submitted | 2013-10-25 |
| Permission granted | 2014-04-30 6 months after submission |
| Operational | 2015-03-19 11 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Central Bedfordshire’s record on solar
Central Bedfordshire has decided 32 solar farms and approved 97%, taking a median of 3.2 months. See every solar farm decision in Central Bedfordshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Caldecote Manor Farm Solar Photovoltaics · Operational | 5 | 7.6 km |
Langford Wind Farm Wind Onshore · Operational | 20 | 10.1 km |
Langford Solar Farm Solar Photovoltaics · Operational | 13 | 12.1 km |
Fairview Farm Solar Photovoltaics · Operational | 0.2 | 12.2 km |
Croydon / Church Farm (Royston) Solar Photovoltaics · Operational | 16.5 | 12.3 km |
Staughton Airfield Solar Farm Solar Photovoltaics · Operational | 40 | 12.5 km |
Cotton Farm Wind Onshore · Operational | 20 | 13.2 km |
Vine Farm Solar Park Solar Photovoltaics · Operational | 45 | 13.5 km |
How big is Waterloo solar park?
Waterloo solar park has a recorded installed capacity of 14.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Waterloo solar park?
REPD records the operator as Lightsource Renewable Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Waterloo solar park approved and built?
The application was submitted on 2013-10-25. Permission was granted on 2014-04-30, 6 months later. The site became operational on 2015-03-19, 11 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1769.