Cotton Farm is operational in Huntingdonshire with a recorded capacity of 20 MW, and has been generating since 2013-03-31.

20 MW
Capacity
as recorded in REPD
Operational
Status
since 2013-03-31
Wind Onshore
Technology
Greencoat UK Wind
Huntingdonshire
Authority
England

Planning and build timeline

Application submitted2008-08-04
Permission granted2010-12-14
28 months after submission
Operational2013-03-31
28 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Huntingdonshire’s record on onshore wind

Huntingdonshire has decided 10 onshore wind schemes and approved 80%, taking a median of 13.9 months. See every onshore wind scheme decision in Huntingdonshire

Other built sites within 15 km

SiteMWDistance
Fairview Farm
Solar Photovoltaics · Operational
0.25.1 km
Station Farm Landfill Scheme
Landfill Gas · Operational
25.6 km
Caldecote Manor Farm
Solar Photovoltaics · Operational
55.7 km
Common Barn Wind Farm
Wind Onshore · Operational
6.26.6 km
Godmanchester
Landfill Gas · Operational
37.3 km
Littleyhey Prison Solar Farm
Solar Photovoltaics · Operational
0.58.4 km
Skylark Meadow Solar park
Solar Photovoltaics · Operational
510.7 km
Meadow Lane Park and Ride
Battery · Under Construction
11.1 km

How big is Cotton Farm?

Cotton Farm has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cotton Farm?

REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cotton Farm approved and built?

The application was submitted on 2008-08-04. Permission was granted on 2010-12-14, 28 months later. The site became operational on 2013-03-31, 28 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3971.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council