Renewable sites › Cotton Farm
Cotton Farm
Cotton Farm is operational in Huntingdonshire with a recorded capacity of 20 MW, and has been generating since 2013-03-31.
Planning and build timeline
| Application submitted | 2008-08-04 |
| Permission granted | 2010-12-14 28 months after submission |
| Operational | 2013-03-31 28 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Huntingdonshire’s record on onshore wind
Huntingdonshire has decided 10 onshore wind schemes and approved 80%, taking a median of 13.9 months. See every onshore wind scheme decision in Huntingdonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Fairview Farm Solar Photovoltaics · Operational | 0.2 | 5.1 km |
Station Farm Landfill Scheme Landfill Gas · Operational | 2 | 5.6 km |
Caldecote Manor Farm Solar Photovoltaics · Operational | 5 | 5.7 km |
Common Barn Wind Farm Wind Onshore · Operational | 6.2 | 6.6 km |
Godmanchester Landfill Gas · Operational | 3 | 7.3 km |
Littleyhey Prison Solar Farm Solar Photovoltaics · Operational | 0.5 | 8.4 km |
Skylark Meadow Solar park Solar Photovoltaics · Operational | 5 | 10.7 km |
Meadow Lane Park and Ride Battery · Under Construction | — | 11.1 km |
How big is Cotton Farm?
Cotton Farm has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cotton Farm?
REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cotton Farm approved and built?
The application was submitted on 2008-08-04. Permission was granted on 2010-12-14, 28 months later. The site became operational on 2013-03-31, 28 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3971.