Renewable sites › Fairview Farm
Fairview Farm
Fairview Farm is operational in Huntingdonshire with a recorded capacity of 0.2 MW, and has been generating since 2021-09-22.
Planning and build timeline
| Application submitted | 2020-03-24 |
| Permission granted | 2020-12-24 9 months after submission |
| Operational | 2021-09-22 9 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Huntingdonshire’s record on solar
Huntingdonshire has decided 33 solar farms and approved 97%, taking a median of 3.2 months. See every solar farm decision in Huntingdonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Cotton Farm Wind Onshore · Operational | 20 | 5.1 km |
Caldecote Manor Farm Solar Photovoltaics · Operational | 5 | 5.2 km |
Skylark Meadow Solar park Solar Photovoltaics · Operational | 5 | 5.6 km |
Godmanchester Landfill Gas · Operational | 3 | 10.3 km |
Station Farm Landfill Scheme Landfill Gas · Operational | 2 | 10.5 km |
Meadow Lane Park and Ride Solar Photovoltaics · Under Construction | 0.9 | 11.3 km |
Meadow Lane Park and Ride Battery · Under Construction | — | 11.3 km |
Common Barn Wind Farm Wind Onshore · Operational | 6.2 | 11.4 km |
How big is Fairview Farm?
Fairview Farm has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Fairview Farm?
REPD records the operator as Bird Brothers. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Fairview Farm approved and built?
The application was submitted on 2020-03-24. Permission was granted on 2020-12-24, 9 months later. The site became operational on 2021-09-22, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7972.