Renewable sites › Staughton Airfield Solar Farm
Staughton Airfield Solar Farm
Staughton Airfield Solar Farm is operational in Huntingdonshire with a recorded capacity of 40 MW, and has been generating since 2020-03-01.
Planning and build timeline
| Application submitted | 2015-06-18 |
| Permission granted | 2015-09-28 3 months after submission |
| Operational | 2020-03-01 53 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Huntingdonshire’s record on solar
Huntingdonshire has decided 33 solar farms and approved 97%, taking a median of 3.2 months. See every solar farm decision in Huntingdonshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Manor Farm - Pertenhall Solar Photovoltaics · Operational | 15 | 5.2 km |
Littleyhey Prison Solar Farm Solar Photovoltaics · Operational | 0.5 | 5.3 km |
Common Barn Wind Farm Wind Onshore · Operational | 6.2 | 6.3 km |
ROOKERY FARM SOLAR FARM Solar Photovoltaics · Operational | 5.3 | 8.7 km |
Twinwoods Heat & Power CHP EfW Incineration · Operational | 3.4 | 10.5 km |
Caldecote Manor Farm Solar Photovoltaics · Operational | 5 | 11 km |
Clapham solar farm Solar Photovoltaics · Operational | 7.5 | 11.2 km |
Cotton Farm Wind Onshore · Operational | 20 | 11.4 km |
How big is Staughton Airfield Solar Farm?
Staughton Airfield Solar Farm has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Staughton Airfield Solar Farm?
REPD records the operator as GreenHedge (BayWa r.e.) / Next Energy Capital. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Staughton Airfield Solar Farm approved and built?
The application was submitted on 2015-06-18. Permission was granted on 2015-09-28, 3 months later. The site became operational on 2020-03-01, 53 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5431.