Caldecote Manor Farm

Caldecote Manor Farm is an operational 5 MW solar farm in Huntingdonshire, generating since 24 February 2016. Planning permission was granted on 7 January 2015, 4 months after submission. Operator of record: Sustain Energy Solutions.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 24 February 2016
Solar Photovoltaics
Technology
Sustain Energy Solutions
Huntingdonshire
Authority
England

Planning and build timeline

Application submitted17 September 2014
Permission granted7 January 2015
4 months after submission
Operational24 February 2016
14 months after consent

Screening a site of your own?

RedlineUK · £39

Huntingdonshire approves 97% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Caldecote Manor Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Huntingdonshire’s record on solar

Huntingdonshire has decided 33 solar farms and approved 97%, taking a median of 3.2 months. See every solar farm decision in Huntingdonshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.25.2 km
Wind Onshore · Operational
205.7 km
Solar Photovoltaics · Operational
14.67.6 km
Solar Photovoltaics · Operational
59.2 km
Wind Onshore · Operational
6.29.3 km
Solar Photovoltaics · Operational
0.510.7 km
Solar Photovoltaics · Operational
4011 km
Landfill Gas · Operational
211 km

How big is Caldecote Manor Farm?

Caldecote Manor Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Caldecote Manor Farm?

REPD records the operator as Sustain Energy Solutions. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Caldecote Manor Farm approved and built?

The application was submitted on 17 September 2014. Permission was granted on 7 January 2015, 4 months later. The site became operational on 24 February 2016, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4825.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode