Renewable sites › Exning
Exning
Exning is operational in East Cambridgeshire with a recorded capacity of 29.9 MW, and has been generating since 2015-03-27.
Planning and build timeline
| Application submitted | 2013-10-22 |
| Permission granted | 2014-07-04 8 months after submission |
| Operational | 2015-03-27 9 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Cambridgeshire’s record on solar
East Cambridgeshire has decided 21 solar farms and approved 100%, taking a median of 3.4 months. See every solar farm decision in East Cambridgeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Burwell - Battery Storage Battery · Operational | 50 | 3.9 km |
Forest Heath Solar Farm Solar Photovoltaics · Operational | 5 | 4.4 km |
Breach Farm - Solar farm Battery · Operational | 0.66 | 4.6 km |
Breach Farm - Solar farm Solar Photovoltaics · Operational | 49.9 | 4.6 km |
Burwell Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 4.8 km |
Goosehall Solar Farm Solar Photovoltaics · Operational | 39.5 | 5.5 km |
Bracks Farm Solar Photovoltaics · Operational | 28 | 7.9 km |
North Angle Farm Solar Photovoltaics · Under Construction | 29.4 | 8.4 km |
How big is Exning?
Exning has a recorded installed capacity of 29.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Exning?
REPD records the operator as Vortex (formerly Sun Edison). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Exning approved and built?
The application was submitted on 2013-10-22. Permission was granted on 2014-07-04, 8 months later. The site became operational on 2015-03-27, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1913.