Great Wilbraham Solar Farm

Great Wilbraham Solar Farm is an operational 38.1 MW solar farm in South Cambridgeshire, generating since 31 March 2015. Planning permission was granted on 28 July 2014, 6 months after submission. Operator of record: Inazin Energy Limited / Low Carbon.

38.1 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2015
Solar Photovoltaics
Technology
Inazin Energy Limited / Low Carbon
South Cambridgeshire
Authority
England

Planning and build timeline

Application submitted14 January 2014
Permission granted28 July 2014
6 months after submission
Operational31 March 2015
8 months after consent

Screening a site of your own?

RedlineUK · £39

South Cambridgeshire approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Great Wilbraham Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

South Cambridgeshire’s record on solar

South Cambridgeshire has decided 41 solar farms and approved 88%, taking a median of 3.9 months. See every solar farm decision in South Cambridgeshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
263.8 km
Solar Photovoltaics · Operational
29.99.1 km
Landfill Gas · Operational
210 km
Battery · Operational
5010.9 km
Solar Photovoltaics · Under Construction
49.911.3 km
Solar Photovoltaics · Operational
39.512.4 km
Solar Photovoltaics · Operational
49.913.1 km
Battery · Operational
0.6613.1 km

How big is Great Wilbraham Solar Farm?

Great Wilbraham Solar Farm has a recorded installed capacity of 38.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Great Wilbraham Solar Farm?

REPD records the operator as Inazin Energy Limited / Low Carbon. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Great Wilbraham Solar Farm approved and built?

The application was submitted on 14 January 2014. Permission was granted on 28 July 2014, 6 months later. The site became operational on 31 March 2015, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1835.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode