Renewable sites › Upper Wick Solar Farm
Upper Wick Solar Farm
Upper Wick Solar Farm is an operational 5 MW solar farm in Stroud, generating since 18 January 2016. Planning permission was granted on 14 January 2015, 2 months after submission. Operator of record: Upper Wick Solar Farm.
Planning and build timeline
| Application submitted | 7 November 2014 |
| Permission granted | 14 January 2015 2 months after submission |
| Operational | 18 January 2016 12 months after consent |
Screening a site of your own?
Stroud approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Upper Wick Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Stroud’s record on solar
Stroud has decided 24 solar farms and approved 88%, taking a median of 3 months. See every solar farm decision in Stroud →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 1.8 km |
Solar Photovoltaics · Operational | 7.7 | 2.6 km |
Solar Photovoltaics · Operational | 0.2 | 4 km |
Solar Photovoltaics · Under Construction | 0.21 | 4.1 km |
Solar Photovoltaics · Operational | 2.2 | 6.6 km |
Wind Onshore · Operational | 1 | 7.3 km |
Wind Onshore · Operational | 2 | 8 km |
Solar Photovoltaics · Operational | 28.5 | 8.3 km |
How big is Upper Wick Solar Farm?
Upper Wick Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Upper Wick Solar Farm?
REPD records the operator as Upper Wick Solar Farm. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Upper Wick Solar Farm approved and built?
The application was submitted on 7 November 2014. Permission was granted on 14 January 2015, 2 months later. The site became operational on 18 January 2016, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4751.
Novarly Parcel · official public data, read properly · parcel.novarly.com