Novarly ParcelRenewable sites

Renewable sitesHillhouse Farm

Hillhouse Farm

Hillhouse Farm is an operational 28.5 MW solar farm in Stroud, generating since 31 March 2015. Planning permission was granted on 8 December 2014, 4 months after submission. Operator of record: Cambridge Solar Power/ Vogt Solar.

28.5 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2015
Solar Photovoltaics
Technology
Cambridge Solar Power/ Vogt Solar
Stroud
Authority
England

Planning and build timeline

Application submitted5 August 2014
Permission granted8 December 2014
4 months after submission
Operational31 March 2015
4 months after consent

Screening a site of your own?

RedlineUK · £39

Stroud approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Hillhouse Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Stroud’s record on solar

Stroud has decided 24 solar farms and approved 88%, taking a median of 3 months. See every solar farm decision in Stroud

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
2.21.9 km
Solar Photovoltaics · Operational
0.84.9 km
Solar Photovoltaics · Under Construction
0.215.5 km
Solar Photovoltaics · Operational
57.2 km
EfW Incineration · Operational
14.58 km
Solar Photovoltaics · Operational
58.3 km
Wind Onshore · Operational
28.3 km
Solar Photovoltaics · Operational
59.9 km

How big is Hillhouse Farm?

Hillhouse Farm has a recorded installed capacity of 28.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Hillhouse Farm?

REPD records the operator as Cambridge Solar Power/ Vogt Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Hillhouse Farm approved and built?

The application was submitted on 5 August 2014. Permission was granted on 8 December 2014, 4 months later. The site became operational on 31 March 2015, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2238.

Novarly Parcel · official public data, read properly · parcel.novarly.com