Building F, Renishaw Factory is operational in Stroud with a recorded capacity of 0.2 MW, and has been generating since 2020-04-01.
Planning and build timeline
| Application submitted | 2018-11-13 |
| Permission granted | 2022-03-04 40 months after submission |
| Operational | 2020-04-01 |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Stroud’s record on solar
Stroud has decided 24 solar farms and approved 88%, taking a median of 3 months. See every solar farm decision in Stroud →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Upper Huntingford Farm Solar Photovoltaics · Operational | 7.7 | 2 km |
Mounteneys and Cherry Rock Wind Turbines Wind Onshore · Operational | 1 | 3.7 km |
Upper Wick Solar Farm Solar Photovoltaics · Operational | 5 | 4 km |
Land At Actrees Farm Solar Photovoltaics · Operational | 5 | 5.8 km |
Rednock School - Solar Panels Solar Photovoltaics · Under Construction | 0.21 | 5.9 km |
Tower Hill Farm Solar Photovoltaics · Operational | 8.1 | 7.6 km |
Larks Green Solar Farm Solar Photovoltaics · Operational | 70 | 9.2 km |
Larks Green Solar Farm Battery · Operational | 49.5 | 9.2 km |
How big is Building F, Renishaw Factory?
Building F, Renishaw Factory has a recorded installed capacity of 0.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Building F, Renishaw Factory?
REPD records the operator as Renishaw Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Building F, Renishaw Factory approved and built?
The application was submitted on 2018-11-13. Permission was granted on 2022-03-04, 40 months later. The site became operational on 2020-04-01.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6742.