Ulnes Walton Energy is an operational 1.3 MW landfill gas site in Chorley, generating since 3 March 2003. Planning permission was granted on 10 May 2000, 4 months after submission. Operator of record: SITA UK.

1.3 MW
Capacity
as recorded in REPD
Operational
Status
since 3 March 2003
Landfill Gas
Technology
SITA UK
Chorley
Authority
England

Planning and build timeline

Application submitted20 January 2000
Permission granted10 May 2000
4 months after submission
Operational3 March 2003
34 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Chorley: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ulnes Walton Energy’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
2.53.4 km
Anaerobic Digestion · Operational
1.93.5 km
Battery · Under Construction
53.9 km
Wind Onshore · Operational
2.34.9 km
Battery · Operational
308.7 km
Landfill Gas · Operational
3.38.7 km
Solar Photovoltaics · Operational
1.39.1 km
Solar Photovoltaics · Operational
3.29.2 km

How big is Ulnes Walton Energy?

Ulnes Walton Energy has a recorded installed capacity of 1.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ulnes Walton Energy?

REPD records the operator as SITA UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ulnes Walton Energy approved and built?

The application was submitted on 20 January 2000. Permission was granted on 10 May 2000, 4 months later. The site became operational on 3 March 2003, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 707.