Renewable sitesClifton Marsh Energy

Clifton Marsh Energy

Clifton Marsh Energy is operational in Fylde with a recorded capacity of 3.3 MW, and has been generating since 2006-07-13.

3.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2006-07-13
Landfill Gas
Technology
SITA UK / Natural Power
Fylde
Authority
England

Planning and build timeline

Application submitted2002-03-19
Permission granted2002-04-24
1 months after submission
Operational2006-07-13
51 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Clifton Marsh Wastewater Treatment Works
Solar Photovoltaics · Operational
1.31.5 km
Clifton Marsh Waste Water Treatment Works
Battery · Operational
21.5 km
Clifton Marsh Wastewater Treatment Works
Solar Photovoltaics · Operational
3.21.9 km
Oakfield Farm
Solar Photovoltaics · Operational
52.3 km
Oakfield Farm - extension
Solar Photovoltaics · Operational
1.72.3 km
Cooper House Farm
Solar Photovoltaics · Operational
55 km
Carver Hay, moss lane
Solar Photovoltaics · Operational
2.55.3 km
Brookhouse Mill
Solar Photovoltaics · Operational
0.35.8 km

How big is Clifton Marsh Energy?

Clifton Marsh Energy has a recorded installed capacity of 3.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Clifton Marsh Energy?

REPD records the operator as SITA UK / Natural Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Clifton Marsh Energy approved and built?

The application was submitted on 2002-03-19. Permission was granted on 2002-04-24, 1 months later. The site became operational on 2006-07-13, 51 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 706.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council