Clifton Marsh Wastewater Treatment Works is an operational 1.3 MW solar farm in Fylde, generating since 22 August 2019. Planning permission was granted on 23 May 2018, 10 months after submission. Operator of record: United Utilities.

1.3 MW
Capacity
as recorded in REPD
Operational
Status
since 22 August 2019
Solar Photovoltaics
Technology
United Utilities
Fylde
Authority
England

Planning and build timeline

Application submitted4 August 2017
Permission granted23 May 2018
10 months after submission
Operational22 August 2019
15 months after consent

Screening a site of your own?

RedlineUK · £39

Fylde approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Clifton Marsh Wastewater Treatment Works’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fylde’s record on solar

Fylde has decided 14 solar farms and approved 86%, taking a median of 4.3 months. See every solar farm decision in Fylde

Other built sites within 15 km

SiteMWDistance
Battery · Operational
20.3 km
Solar Photovoltaics · Operational
3.20.4 km
Landfill Gas · Operational
3.31.5 km
Solar Photovoltaics · Operational
52.5 km
Solar Photovoltaics · Operational
1.72.7 km
Solar Photovoltaics · Operational
53.7 km
Solar Photovoltaics · Operational
2.55.8 km
Anaerobic Digestion · Operational
16.8 km

How big is Clifton Marsh Wastewater Treatment Works?

Clifton Marsh Wastewater Treatment Works has a recorded installed capacity of 1.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Clifton Marsh Wastewater Treatment Works?

REPD records the operator as United Utilities. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Clifton Marsh Wastewater Treatment Works approved and built?

The application was submitted on 4 August 2017. Permission was granted on 23 May 2018, 10 months later. The site became operational on 22 August 2019, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6466.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode