Renewable sites › Popehill Farm
Popehill Farm
Popehill Farm is operational in Pembrokeshire with a recorded capacity of 5 MW, and has been generating since 2017-03-29.
Planning and build timeline
| Application submitted | 2015-10-08 |
| Permission granted | 2016-05-18 7 months after submission |
| Operational | 2017-03-29 10 months after consent |
Pembrokeshire’s record on solar
Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
North Tenement Solar Photovoltaics · Operational | 5 | 0.4 km |
Lawrence Landfill Wind Onshore · Operational | 1.6 | 0.9 km |
Bolton Hill WTW Solar Photovoltaics · Operational | 0.5 | 2.6 km |
Cuckoo Grove Farm Solar Photovoltaics · Operational | 6.1 | 4.3 km |
Tiers Cross Solar Farm Solar Photovoltaics · Operational | 24 | 4.6 km |
Shoals Hook Farm Solar Photovoltaics · Operational | 12.1 | 5.4 km |
Puffin Produce - Solar Panels Solar Photovoltaics · Operational | — | 6 km |
Castle Pill - Repowering Wind Onshore · Operational | 3.2 | 6.2 km |
How big is Popehill Farm?
Popehill Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Popehill Farm?
REPD records the operator as North Tenement Solar Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Popehill Farm approved and built?
The application was submitted on 2015-10-08. Permission was granted on 2016-05-18, 7 months later. The site became operational on 2017-03-29, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6108.