Renewable sites › Toggam Farm - Anaerobic Digestion Plant
Toggam Farm - Anaerobic Digestion Plant
Toggam Farm - Anaerobic Digestion Plant is operational in West Suffolk with a recorded capacity of 1 MW, and has been generating since 2022-03-01.
Planning and build timeline
| Application submitted | 2019-12-19 |
| Permission granted | 2020-04-17 4 months after submission |
| Operational | 2022-03-01 22 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Toggam Farm Solar Photovoltaics · Operational | 12.5 | 0.5 km |
May Farm Anaerobic Digester (Farm AD) Anaerobic Digestion · Operational | 2.4 | 10.8 km |
Meadow Farm solar park Solar Photovoltaics · Operational | 6 | 12.3 km |
Hall Farm, West End Northwold - Solar Farm Battery · Operational | 7.5 | 13.2 km |
Hall Farm, West End Northwold - Solar Farm Solar Photovoltaics · Operational | 10 | 13.2 km |
Bay Farm Solar Photovoltaics · Operational | 8.1 | 13.2 km |
Reaches Farm Solar Park Solar Photovoltaics · Operational | 6.1 | 14.4 km |
Thetford Biomass Power Station Biomass (dedicated) · Operational | 38.5 | 14.9 km |
How big is Toggam Farm - Anaerobic Digestion Plant?
Toggam Farm - Anaerobic Digestion Plant has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Toggam Farm - Anaerobic Digestion Plant?
REPD records the operator as Greenheath Farming Co Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Toggam Farm - Anaerobic Digestion Plant approved and built?
The application was submitted on 2019-12-19. Permission was granted on 2020-04-17, 4 months later. The site became operational on 2022-03-01, 22 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11240.