Novarly ParcelRenewable planning

Renewable planning SolarManchester

Solar planning in Manchester

Manchester has decided 45 solar farms and approved 91% of them, taking a median of 1.7 months to decide. Consented capacity: 20 MW. 3 applications still awaiting a decision.

91%
Approved
41 granted · 4 refused
1.7 mo
Median decision
UK 2.3 mo
20 MW
Consented
2 MW refused
0
Appeals
no appeals recorded

How Manchester compares

Against the 298 UK authorities with 5+ solar decisions, Manchester sits in the 27th percentile for approval rate (2 points below the England average) and the 87th percentile for speed.

Decisions by year

1020Approved — 1 (2019)119Approved — 3 (2020)320Approved — 4 (2021)421Approved — 5 (2022)522Approved — 7 (2023)723Approved — 6 (2024)624Approved — 12 (2025)Refused — 4 (2025)1625Approved — 3 (2026)326
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (51)

SchemeMWStatusDecided
Sunbank Lane - Solar Panels
Igen Energy Limited · 145280/P14J/2026
4.3Application Submitted2026-02-26
Manchester Royal Infirmary, Oxford Road - Solar Panels
Manchester University NHS Foundation Trust · 144729/FO/2025 · 2.4 mo to decide
Awaiting Construction2026-02-19
Riverside Works, Collyhurst Road - Solar Panels
Clearvolt Limited · 144878/P14J/2026 · 1 mo to decide
0.46Awaiting Construction2026-02-05
Acute Building, Southmoor Road - Solar Panels
Manchester University NHS Foundation Trust (North Western RHA) · 144635/P14J/2025 · 1.8 mo to decide
0.48Awaiting Construction2026-01-21
Co Op Academy Belle Vue, Hyde Road - Solar Panels
Co-op Academy Trust · 144932/P14J/2026
0.16Application Submitted2026-01-13
Manchester Academy, Moss Lane East - Solar Panels
Manchester Academy · 144528/P14J/2025 · 1.1 mo to decide
0.17Awaiting Construction2025-12-18
The Windrush Millenium Centre, Alexandra Road - Solar Panels
DVC Group Limited · 144397/P14J/2025 · 1.1 mo to decide
Awaiting Construction2025-12-02
Gorton Education Village, Wembley Road - Solar Panels
Gorton education Village · 144168/P14J/2025 · 1.8 mo to decide
0.6Awaiting Construction2025-11-25
Loreto College, Chichester Road - Solar Panels
Energy Group plc · 143800/FO/2025 · 1.6 mo to decide
0.36Awaiting Construction2025-10-10
Whalley Range High School, Wilbraham Road - Solar Panels
Whalley Range 11 - 18 High Schoo · 143625/P14J/2025 · 1.7 mo to decide
0.39Awaiting Construction2025-09-23
East Manchester Academy, Grey Mare Lane - Solar Panels
East Manchester Academy · 143624/P14J/2025 · 1.5 mo to decide
0.23Awaiting Construction2025-09-15
Dixons Brooklands Academy, Moor Road - Solar Panels
Located Property Limited · 143526/P14J/2025 · 1.4 mo to decide
0.22Awaiting Construction2025-09-02
The Printworks, Withy Grove - Solar Panels
DTZ Investors UK · 143290/P14J/2025 · 1.6 mo to decide
0.22Awaiting Construction2025-08-11
Dnata City North, Pinfold Lane - Solar Panels
Dnata Ltd · 143250/P14J/2025 · 1.3 mo to decide
0.33Awaiting Construction2025-07-28
Thg Icon, Sunbank Lane, Unit 2 - Solar Array
Olympus Power · 142926/P14J/2025 · 1.7 mo to decide
0.82Application Refused2025-07-03
Thg Studio, Sunbank Lane - Solar Panels
Olympus Power · 142924/P14J/2025 · 1.7 mo to decide
0.41Application Refused2025-07-02
Thg Icon, Sunbank Lane -Solar Array
Olympus Power · 142925/P14J/2025 · 1.7 mo to decide
0.16Application Refused2025-07-02
Etihad Stadium, Ashton New Road - Solar Panels
Manchester City Football Club · 142350/P14J/2025 · 1.8 mo to decide
0.22Awaiting Construction2025-05-01
Styal Road - Solar Panels
RR UK (South) Limited · 142111/P14J/2025 · 1.7 mo to decide
0.16Application Refused2025-04-04
DHL Express Manchester, Sunbank Lane - Solar Panels
Aberla Energy · 141616/P14J/2024 · 1.7 mo to decide
0.29Awaiting Construction2025-01-20
Endress & Hauser, Floats Road - Solar PV panels
Endress & Hauser Limited · 141518/P14J/2024 · 1.8 mo to decide
0.4Awaiting Construction2025-01-10
City Football Academy - Solar Panels
Manchester City Football Club · 141212/FO/2024 · 1.8 mo to decide
1.12Awaiting Construction2024-12-17
New Smithfield Market, Whitworth Street East -Solar Panels
Private Developer · 141249/P14J/2024 · 1.8 mo to decide
0.27Awaiting Construction2024-12-10
New Smithfield Market - Solar Panels
Private Developer · 141251/P14J/2024 · 1.8 mo to decide
0.16Awaiting Construction2024-12-10
Duo Plastics Limited, Vickers Street - Solar Panels
Ashcroft Electrical Services Limited · 141102/P14J/2024
0.56Application Submitted2024-09-24
Manchester Marriott Victoria And Albert Hotel - Solar Panels
Marriott Hotels · 138448/FO/2023 · 6.8 mo to decide
0.17Abandoned2024-06-25
City Football Academy, Ashton New Road - Solar panels
Manchester City Football Club · 139535/P14J/2024 · 1.4 mo to decide
3.38Under Construction2024-04-26
Xaverian College, Lower Park Road - Solar Panels
Avrenim · 139339/FO/2024 · 13.3 mo to decide
0.17Awaiting Construction2024-04-16
Scotscroft Towers Business Park, Wilmslow Road - Solar Panels
Kennedy Wilson · 138923/P14J/2023 · 0.9 mo to decide
0.15Awaiting Construction2024-02-21
Ymca And Castlefield Hotel, Liverpool Road - Solar Panels
Manchester YMCA & Castlefield Hotel · 138882/P14J/2023
0.2Application Withdrawn2024-02-13
Hammerstone Road Depot - Solar Panels
Manchester City Council · 138157/VO/2023 · 1.4 mo to decide
Awaiting Construction2023-11-02
Manchester Communication Academy, Silchester Drive - Solar Panels
Energy Intelligence Limited · 136761/P14J/2023 · 1.3 mo to decide
0.26Awaiting Construction2023-09-25
Unit C, Kelbrook Road - Solar Panels
Cascade UK Limited · 137495/P14J/2023 · 1.8 mo to decide
0.61Awaiting Construction2023-08-30
Manchester Academy, Moss Lane East - Solar Panels
United Learning Trust · 137313/FO/2023 · 1.3 mo to decide
Awaiting Construction2023-08-22
Reliance Trading Estate,Reliance Street - Solar Panels
Private Developer · 137312/P14J/2023 · 1.8 mo to decide
0.42Awaiting Construction2023-08-21
Manchester Metropolitan University, Birley Fields - Solar Panels
Manchester Metropolitan University · 137434/P14J/2023 · 1.5 mo to decide
0.2Awaiting Construction2023-08-10
G H Sheldon, Stainburn Road - Solar Panels
Clear Volt Limited · 136836/P14J/2023 · 1.6 mo to decide
0.29Awaiting Construction2023-07-04
The National Cycling Centre - Solar Photovoltaic Panels
Manchester City Council · 133359/VO/2022 · 4.3 mo to decide
0.92Under Construction2022-08-16
Royal Northern College Of Music, Oxford Road - Solar Photovoltaic panels
Royal Northern College Of Music · 131256/FO/2021 · 11.6 mo to decide
0.17Under Construction2022-07-22
Ashton Old Road - Solar Panels
The Manchester College · 133313/P14J/2022 · 1.6 mo to decide
0.39Awaiting Construction2022-06-10
Timpson Road - Solar Panels
Private Developer · 133496/P14J/2022 · 1.3 mo to decide
0.47Awaiting Construction2022-05-16
Wythenshawe Hospital - Solar photovoltaic
University Hospital of South Manchester (UHSM) NHS Foundation Trust · 133140/P14J/2022 · 2.1 mo to decide
0.45Awaiting Construction2022-05-06
Wythenshawe Hospital - Solar Array
South Manchester University Hospital NHS Trust · 132669/LP/2022
0.57Application Withdrawn2022-03-07
Outer Space Studios Solar Panels
Ameresco Limited · 130665/P14J/2021 · 5.1 mo to decide
0.6Operational2021-11-04
Central Park - Solar photovaltics
Greater Manchester Police · 130821/P14J/2021 · 2.7 mo to decide
0.15Operational2021-09-15
The Sharp Project - Solar panels
Ameresco Limited · 130663/P14J/2021 · 2.2 mo to decide
0.27Awaiting Construction2021-08-06
Sunbank Lane Solar Panels
Zestec Asset Management · 130585/FO/2021 · 1.3 mo to decide
1.51Awaiting Construction2021-07-06
The National Cycling Centre Velodrome
Manchester City Council · 127681/VO/2020 · 1.7 mo to decide
0.7Operational2020-10-30
Tesco Burnage Store
Tesco Stores · 125482/P14J/2019 · 1.8 mo to decide
1Awaiting Construction2020-01-15
Tesco Store East Didsbury
Tesco Stores · 125481/P14J/2019 · 1.8 mo to decide
1Awaiting Construction2020-01-15
Tesco Super-Store (Garratt Way, Gorton)
Push Energy · 122212/P14J/2018 · 1.9 mo to decide
0.7Operational2019-03-01

Does Manchester approve solar farms?

Yes — of the 45 solar farms Manchester has decided, 91% were approved (41 granted, 4 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Manchester?

The median time from application to decision is 1.7 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Manchester consented?

20 MW has been consented across 41 approved schemes, with 2 MW refused. A further 3 applications awaits a decision.

Other technologies in Manchester

Battery storage in ManchesterOnshore wind in Manchester

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.