Novarly ParcelRenewable sites

Renewable sitesThe Manor of Cadland Estate - extension

The Manor of Cadland Estate - extension

The Manor of Cadland Estate - extension is operational in New Forest with a recorded capacity of 3 MW, and has been generating since 2014-02-07.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-02-07
Solar Photovoltaics
Technology
Manor of Cadland
New Forest
Authority
England

Planning and build timeline

Application submitted2013-04-30
Permission granted2013-07-18
3 months after submission
Operational2014-02-07
7 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

New Forest’s record on solar

New Forest has decided 20 solar farms and approved 75%, taking a median of 2.2 months. See every solar farm decision in New Forest

Other built sites within 15 km

SiteMWDistance
The Manor of Cadland Estate
Solar Photovoltaics · Operational
50.5 km
Fawley Waste to Energy Plant
EfW Incineration · Operational
8.64.6 km
Netley Landfill Site, Hampshire (Extension)
Landfill Gas · Operational
1.29 km
Netley Landfill Solar
Solar Photovoltaics · Operational
129.2 km
Chawton Farm Solar Farm
Solar Photovoltaics · Operational
3.29.2 km
Concorde Way, Segensworth - Solar Panels
Solar Photovoltaics · Under Construction
1.0410.4 km
Greenhill Anaerobic Digestion Plant
Anaerobic Digestion · Operational
110.9 km
Durrants Farm Solar
Solar Photovoltaics · Operational
4.511.1 km

How big is The Manor of Cadland Estate - extension?

The Manor of Cadland Estate - extension has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates The Manor of Cadland Estate - extension?

REPD records the operator as Manor of Cadland. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was The Manor of Cadland Estate - extension approved and built?

The application was submitted on 2013-04-30. Permission was granted on 2013-07-18, 3 months later. The site became operational on 2014-02-07, 7 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1669.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council