Renewable sites › Easington Farm (Chalgrove)
Easington Farm (Chalgrove)
Easington Farm (Chalgrove) is an operational 21.3 MW solar farm in South Oxfordshire, generating since 17 March 2015. Planning permission was granted on 14 August 2014, 2 months after submission. Operator of record: Chalgrove Solar.
Planning and build timeline
| Application submitted | 3 June 2014 |
| Permission granted | 14 August 2014 2 months after submission |
| Operational | 17 March 2015 7 months after consent |
Screening a site of your own?
South Oxfordshire approves 95% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Easington Farm (Chalgrove)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
South Oxfordshire’s record on solar
South Oxfordshire has decided 22 solar farms and approved 95%, taking a median of 4.2 months. See every solar farm decision in South Oxfordshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 2.4 | 2.8 km |
Solar Photovoltaics · Operational | 0.3 | 7.1 km |
Solar Photovoltaics · Operational | 7 | 7.2 km |
Anaerobic Digestion · Operational | 2.4 | 7.3 km |
Anaerobic Digestion · Operational | 2.3 | 7.3 km |
Battery · Operational | 49.9 | 10.2 km |
Solar Photovoltaics · Operational | 1.2 | 10.5 km |
Solar Photovoltaics · Operational | 3 | 11.6 km |
How big is Easington Farm (Chalgrove)?
Easington Farm (Chalgrove) has a recorded installed capacity of 21.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Easington Farm (Chalgrove)?
REPD records the operator as Chalgrove Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Easington Farm (Chalgrove) approved and built?
The application was submitted on 3 June 2014. Permission was granted on 14 August 2014, 2 months later. The site became operational on 17 March 2015, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2333.