Novarly ParcelRenewable sites

Renewable sitesTappaghan Extension

Tappaghan Extension

Tappaghan Extension is an operational 9 MW onshore wind farm in Fermanagh and Omagh, generating since 1 July 2009. Planning permission was granted on 1 May 2008, 35 months after submission. Operator of record: Greencoat UK Wind.

9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2009
Wind Onshore
Technology
Greencoat UK Wind
Fermanagh and Omagh
Authority
Northern Ireland

Planning and build timeline

Application submitted12 June 2005
Permission granted1 May 2008
35 months after submission
Operational1 July 2009
14 months after consent

Screening a site of your own?

RedlineUK · £39

Fermanagh and Omagh approves 92% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Tappaghan Extension’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Fermanagh and Omagh’s record on onshore wind

Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
19.50 km
Wind Onshore · Operational
32.211 km
Wind Onshore · Operational
9.211 km
Wind Onshore · Operational
9.211 km
Wind Onshore · Operational
10.511.3 km
Wind Onshore · Operational
2511.7 km
Wind Onshore · Operational
18.411.9 km
Wind Onshore · Operational
912 km

How big is Tappaghan Extension?

Tappaghan Extension has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tappaghan Extension?

REPD records the operator as Greencoat UK Wind. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tappaghan Extension approved and built?

The application was submitted on 12 June 2005. Permission was granted on 1 May 2008, 35 months later. The site became operational on 1 July 2009, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4688.